1852 1/2 W BROWNING BLVD 90062

Certificate Information: 1852 1/2 W BROWNING BLVD 90062

Application / Permit
21014-30000-05076
Plan Check / Job No.
B21WL04431
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
convert existing detached garage to (2) ADUs with addition
Permit Issued
Issued on 8/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 TARIK SAOUD
Corrections Issued 10/17/2021 TARIK SAOUD
Quality Review Completed 10/26/2021 CHIHARU SUZUKI
Plan Check Approved 8/3/2022 TARIK SAOUD
Building Plans Picked Up 8/4/2022 APPLICANT
Issued 8/18/2022 APPLICANT
CofO in Progress 8/23/2024 SABAS ALONSO
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/10/2021 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 11/15/2021 AMAAN MALIK
Sewer availability Cleared 11/15/2021 AMAAN MALIK
ZI Cleared 2/22/2022 RAFAEL FONTES
Low Impact Development Cleared 6/20/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 6/23/2022 AMAAN MALIK

Contact Information

Contractor Builder Point Construction; Lic. No.: 1059885-B 11445 PARAMOUNT BLVD SUITE H      DOWNEY, CA 90241
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/5/2023 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 7/5/2023 Corrections Issued SABAS ALONSO
Underground Mechanical 7/5/2023 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 7/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 8/28/2023 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 8/30/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 11/14/2023 Approved SABAS ALONSO
Green Building Rough 11/14/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/4/2023 Approved SABAS ALONSO
Rough-Elec/Plmb/HVAC 12/4/2023 Approved SABAS ALONSO
Insulation 12/11/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 12/11/2023 Partial Approval SABAS ALONSO
Sewer 12/11/2023 Corrections Issued SABAS ALONSO
Drywall Nailing 12/21/2023 Approved JOSH MEISTER
Sewer 1/26/2024 Approved SABAS ALONSO
Underground Mechanical 1/26/2024 Approved SABAS ALONSO
Final 5/6/2024 Corrections Issued SABAS ALONSO
Green Building Final 5/6/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/6/2024 SGSOV Approved SABAS ALONSO
Smoke Detectors 5/6/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 8/15/2024 Corrections Issued CRAIG DAVIS
Final 8/15/2024 Corrections Issued CRAIG DAVIS
HVAC-Final 8/15/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Final 8/15/2024 Corrections Issued CRAIG DAVIS
Smoke Detectors 8/15/2024 Approved CRAIG DAVIS
Final 8/22/2024 OK to Issue CofO SABAS ALONSO