511 S CASHMERE TER 90049
Certificate Information: 511 S CASHMERE TER 90049
- Application / Permit
- 21014-30000-05040
- Plan Check / Job No.
- B21WL04405
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and Remodel to (E) 1-Story S.F.D
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- CofO Issued on 10/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | DAVID CASTILLO |
| Corrections Issued | 11/3/2021 | DAVID CASTILLO |
| Quality Review Completed | 11/16/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 1/18/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 2/14/2022 | DAVID CASTILLO |
| Plan Check Approved | 3/11/2022 | DAVID CASTILLO |
| Issued | 3/16/2022 | APPLICANT |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| CofO in Progress | 10/14/2023 | CARLOS MATAMOROS |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
| CofO Issued | 10/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 12/20/2021 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/29/2021 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 1/31/2022 | SUNG JOON WON |
| Grading Pre-Inspection | Cleared | 2/14/2022 | DAVID CASTILLO |
| Roof/Waste drainage to street | Cleared | 3/11/2022 | STEVEN JIN |
Contact Information
| Architect | Urman,, Janet Metson; Lic. No.: C18003 | 6636 MARYLAND DRIVE LOS ANGELES, CA 90048 |
| Contractor | Horgan William Daniel; Lic. No.: 444426-B | 7936 SEDAN AVENUE WEST HILLS, CA 91304 |
| Engineer | Resnick,, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/10/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Inspection | 5/10/2022 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/24/2022 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/26/2022 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 6/7/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Corrections Issued | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 6/15/2022 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/15/2022 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 9/23/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/23/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 10/14/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 10/21/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 11/3/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 11/3/2022 | Partial Approval | CARLOS MATAMOROS |
| MERV13>=Rough | 11/3/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 11/16/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 11/16/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 11/16/2022 | Approved | CARLOS MATAMOROS |
| Insulation | 11/23/2022 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 12/2/2022 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 12/9/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 12/13/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 12/16/2022 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/12/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 3/6/2023 | Conditional Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/6/2023 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 3/23/2023 | Corrections Issued | JESUS PINEDA |
| Shower Pan | 3/24/2023 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 3/29/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/30/2023 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 3/31/2023 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 6/5/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 6/5/2023 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 6/5/2023 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/14/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 9/14/2023 | Approved | CARLOS MATAMOROS |
| Final | 9/14/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Final | 9/14/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 9/14/2023 | Approved | CARLOS MATAMOROS |
| MERV13>=Final | 9/14/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 9/14/2023 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/14/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 9/14/2023 | Approved | CARLOS MATAMOROS |
| Final | 9/22/2023 | Corrections Issued | CARLOS MATAMOROS |
| Final | 10/13/2023 | OK to Issue CofO | CARLOS MATAMOROS |