1245 S CAMDEN DR 90035

Certificate Information: 1245 S CAMDEN DR 90035

Application / Permit
21014-30000-05036
Plan Check / Job No.
B21WL04396
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
addition and renovation to (e) two story single family house
Permit Issued
Issued on 2/9/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 FELIPE HERNANDEZ
Corrections Issued 10/21/2021 FELIPE HERNANDEZ
Quality Review Completed 11/1/2021 TARIK SAOUD
Applicant returned to address corrections 8/25/2022 FELIPE HERNANDEZ
Building Plans Picked Up 8/30/2022 APPLICANT
Applicant returned to address corrections 9/12/2022 CHIHARU SUZUKI
Applicant returned to address corrections 9/15/2022 CHIHARU SUZUKI
Applicant returned to address corrections 11/8/2022 CHIHARU SUZUKI
Plan Check Approved 11/15/2022 CHIHARU SUZUKI
Issued 2/9/2023 APPLICANT
CofO in Progress 12/17/2024 ARAM AVEDISIAN
CofO Issued 12/18/2024 RICHARD STEINBACH
Permit Finaled 12/18/2024 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 11/19/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/24/2021 DINAH GARIN
Grading Pre-Inspection Cleared 12/8/2021 VASIL MIHALEV
ZA Case Cleared 12/17/2021 KENTON TRINH
Low Impact Development Cleared 7/25/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 7/27/2022 DINAH GARIN

Contact Information

Contractor Zeidan Nabil R; Lic. No.: 1078391-B 8886 DEERWEED CIR      CORONA, CA 92883
Engineer Dallalzadeh,, Curesh; Lic. No.: M26425 1659 WELLESLEY AVE      LOS ANGELES, CA 90025
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/20/2023 Conditional Approval ASHLEY THOMPSON
Footing/Foundation/Slab 3/31/2023 Approved JEREMY TODD
METHANE-Barrier 3/31/2023 Approved JEREMY TODD
METHANE-Subgrade 3/31/2023 Approved JEREMY TODD
Deputy Reinf. Concrete 4/4/2023 Conditional Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 4/12/2023 Partial Approval MICHAEL PELHAM
Green Building Rough 4/12/2023 Not Ready for Inspection MICHAEL PELHAM
METHANE-Rough 4/12/2023 Approved MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 4/19/2023 Approved JEREMY TODD
Deputy Wood Construction 6/22/2023 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/2/2023 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 10/12/2023 Partial Approval MEL KHACHATOURIAN
HVAC-Rough 10/12/2023 Approved MEL KHACHATOURIAN
PLUMBING-Rough 10/12/2023 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 11/2/2023 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 11/2/2023 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 11/2/2023 Approved MEL KHACHATOURIAN
Insulation 11/14/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/14/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Shower Pan 11/14/2023 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 11/20/2023 Approved OGANES TARAKHCHYAN
Green Building Rough 11/20/2023 Approved OGANES TARAKHCHYAN
Insulation 11/20/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/20/2023 Approved OGANES TARAKHCHYAN
Wood Frame 11/20/2023 Approved OGANES TARAKHCHYAN
Drywall Nailing 11/27/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 9/13/2024 Corrections Issued ASHLEY THOMPSON
Final 9/13/2024 Corrections Issued ASHLEY THOMPSON
Green Building Final 9/13/2024 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Final 9/13/2024 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 9/13/2024 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 10/9/2024 Approved ASHLEY THOMPSON
Final 10/9/2024 Not Ready for Inspection ASHLEY THOMPSON
Gas Test 10/9/2024 Corrections Issued ASHLEY THOMPSON
Green Building Final 10/9/2024 Corrections Issued ASHLEY THOMPSON
HVAC-Final 10/9/2024 Corrections Issued ASHLEY THOMPSON
PLUMBING-Final 10/9/2024 Corrections Issued ASHLEY THOMPSON
Smoke Detectors 10/9/2024 Not Ready for Inspection ASHLEY THOMPSON
Final 11/19/2024 Corrections Issued STEPHANIE SWANSON
Green Building Final 11/19/2024 Approved STEPHANIE SWANSON
HVAC-Final 11/19/2024 Approved STEPHANIE SWANSON
PLUMBING-Final 11/19/2024 Approved STEPHANIE SWANSON
Smoke Detectors 11/19/2024 Not Ready for Inspection STEPHANIE SWANSON
Final 12/17/2024 OK to Issue CofO ARAM AVEDISIAN
Smoke Detectors 12/17/2024 Approved ARAM AVEDISIAN