1421 N GENESEE AVE 90046
Certificate Information: 1421 N GENESEE AVE 90046
- Application / Permit
- 21014-30000-05032
- Plan Check / Job No.
- B21WL04387
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached two car garage to Accessory Dwelling Unit per GCS 65852.2.(e).(1).(A) with 122 SF addition for ingress/egress only.
- Permit Issued
- Issued on 4/25/2022
- Issuing Office
- Current Status
- CofO Issued on 7/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | JASON JANGADA |
| Corrections Issued | 10/18/2021 | JASON JANGADA |
| Applicant returned to address corrections | 2/22/2022 | RICARDO RAMIREZ |
| Plan Check Approved | 3/30/2022 | KHUONG TRUONG |
| Issued | 4/25/2022 | APPLICANT |
| Building Plans Picked Up | 4/29/2022 | APPLICANT |
| CofO in Progress | 7/27/2023 | STUART CHAPMAN |
| Permit Finaled | 7/30/2023 | DEROLD HAUFF |
| CofO Issued | 7/30/2023 | DEROLD HAUFF |
| Permit Finaled | 7/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 1/11/2022 | AMANDA KAINER |
| HPOZ | Cleared | 1/11/2022 | AMANDA KAINER |
| Miscellaneous | Cleared | 1/11/2022 | AMANDA KAINER |
| ZI | Cleared | 1/11/2022 | AMANDA KAINER |
| Hydrant and Access approval | Cleared | 2/3/2022 | JOHN CONNEALLY |
| Address approval | Cleared | 2/8/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 2/8/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 2/11/2022 | CHRISTOPHER ROCHA |
| Construction near power lines | Cleared | 2/15/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Derleth Custom Construction Inc; Lic. No.: 830190-B | 578 WASHINGTON BLVD #207 MARINA DEL REY, CA 90292 |
| Engineer | Tabirara,, Vernon Nicolas; Lic. No.: C75492 | 17520 DAPHNE AVE TORRANCE, CA 90504 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/13/2022 | Conditional Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 9/26/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 9/26/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 9/26/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/26/2022 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 10/26/2022 | Partial Inspection | RAUL BARAJAS |
| Green Building Rough | 10/26/2022 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 10/26/2022 | Partial Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 10/31/2022 | Conditional Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 10/31/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/31/2022 | Approved | BRIAN SULLIVAN |
| Insulation | 11/9/2022 | Partial Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 11/9/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 12/8/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/29/2023 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 6/29/2023 | Approved | RAUL BARAJAS |
| Final | 6/29/2023 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/29/2023 | Approved | RAUL BARAJAS |
| Green Building Final | 6/29/2023 | Approved | RAUL BARAJAS |
| HVAC-Final | 6/29/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 6/29/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 6/29/2023 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/13/2023 | Approved | STUART CHAPMAN |
| Final | 7/13/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 7/27/2023 | OK to Issue CofO | STUART CHAPMAN |