9415 W CRESTA DR 90035
Certificate Information: 9415 W CRESTA DR 90035
- Application / Permit
- 21014-30000-04989
- Plan Check / Job No.
- B21WL04373
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) 1/2 bathroom attached to an existing 2-car garage. Per engineering design.
- Permit Issued
- Issued on 10/24/2022
- Issuing Office
- Current Status
- Issued on 10/24/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2021 | ALFREDO JARA |
| Corrections Issued | 10/6/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 2/10/2022 | MANUEL GARCIA |
| Applicant returned to address corrections | 3/1/2022 | JASON JANGADA |
| Plan Check Approved | 10/12/2022 | ALFREDO JARA |
| Issued | 10/24/2022 | APPLICANT |
| Building Plans Picked Up | 10/26/2022 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/25/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 2/4/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | DINAH GARIN |
Contact Information
| Contractor | Corner Construction Co Inc; Lic. No.: 301167-B | 865 VIA DE LA PAZ #203 PACIFIC PALISADES, CA 90272 |
| Engineer | Gorgy,, Moheb Shohdy; Lic. No.: C53260 | 1545 VICTORY BLVD STE 102 GLENDALE, CA 91201 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/8/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 11/8/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Underground Mechanical | 2/7/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/8/2023 | Corrections Issued | DAVID FEILER |
| Underground Mechanical | 3/9/2023 | Partial Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 3/28/2023 | Approved | ASHLEY THOMPSON |
| METHANE-Barrier | 3/28/2023 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 3/28/2023 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 4/20/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 4/20/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| METHANE-Rough | 4/20/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 4/28/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 4/28/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 4/28/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 4/28/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 5/8/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Partial Approval | CLAYTON GRAHAM |
| Green Building Rough | 5/8/2023 | Approved | CLAYTON GRAHAM |
| Insulation | 5/8/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 5/8/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 5/11/2023 | Approved | CLAYTON GRAHAM |