1603 W 247TH PL 90710
Certificate Information: 1603 W 247TH PL 90710
- Application / Permit
- 21014-30000-04987
- Plan Check / Job No.
- B21WL04369
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Detached Garage Conversion to ADU and Addition per GCS65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/28/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | MANUEL GARCIA |
| Corrections Issued | 10/8/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 7/1/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 7/7/2022 | APPLICANT |
| Applicant returned to address corrections | 7/26/2022 | RICHARD GARCIA |
| Plan Check Approved | 8/23/2022 | JASON JANGADA |
| Issued | 3/28/2023 | APPLICANT |
| CofO in Progress | 9/6/2023 | EUGENE CASSIDY |
| CofO Issued | 10/12/2023 | ANSON MAGLASANG |
| Permit Finaled | 10/12/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2021 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 12/1/2021 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | JOSE HERNANDEZ |
| Construction near power lines | Cleared | 2/15/2022 | RIDWAN HARDY |
| Sewer availability | Cleared | 4/5/2022 | JOSE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Durand,, Paul H; Lic. No.: S4222 | 611 N G ST OXNARD, CA 93030 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/3/2023 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/3/2023 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 4/3/2023 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 4/3/2023 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 4/3/2023 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/11/2023 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 4/11/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 4/11/2023 | Approved | EUGENE CASSIDY |
| Wood Frame | 4/11/2023 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/20/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/20/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 4/20/2023 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 4/20/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/20/2023 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 4/20/2023 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 4/24/2023 | Conditional Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/27/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 4/27/2023 | Approved | EUGENE CASSIDY |
| Gas Test | 4/27/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/27/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 4/27/2023 | Approved | EUGENE CASSIDY |
| Sewer | 4/27/2023 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 4/27/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/11/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/11/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 5/11/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 5/11/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 5/11/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/11/2023 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 5/11/2023 | Not Required | EUGENE CASSIDY |
| Smoke Detectors | 5/11/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/16/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 5/16/2023 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Final | 5/16/2023 | Approved | EUGENE CASSIDY |
| Service/Power Release | 5/16/2023 | Not Required | EUGENE CASSIDY |
| Final | 6/5/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 6/5/2023 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 6/5/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 8/29/2023 | Corrections Issued | EUGENE CASSIDY |
| Smoke Detectors | 8/29/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 9/5/2023 | Approved | EUGENE CASSIDY |
| Final | 9/5/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 9/5/2023 | Approved | EUGENE CASSIDY |