15614 W MORRISON ST 91403

Certificate Information: 15614 W MORRISON ST 91403

Application / Permit
21014-30000-04972
Plan Check / Job No.
B21WL04359
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground floor addition to an existing S.F.D.
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 12/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2021 APPLICANT
Assigned to Plan Check Engineer 10/6/2021 KHUONG TRUONG
Corrections Issued 10/6/2021 KHUONG TRUONG
Applicant returned to address corrections 11/15/2021 JASON JANGADA
Applicant returned to address corrections 12/8/2021 KHUONG TRUONG
Plan Check Approved 1/3/2022 RICHARD GARCIA
Issued 1/12/2022 APPLICANT
Building Plans Picked Up 1/19/2022 APPLICANT
CofO in Progress 12/3/2025 SEAN WIRCH
Permit Finaled 12/6/2025 MICHAEL PELHAM
CofO Issued 12/6/2025 MICHAEL PELHAM
Permit Finaled 12/6/2025 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/29/2021 DAGOVERTO GUERRERO
ZA Case Cleared 10/29/2021 RICHARD REASER
Roof/Waste drainage to street Cleared 12/13/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Rhino Construction Group Inc; Lic. No.: 852063-B 12207 WILSHIRE BLVD #203      LOS ANGELES, CA 90025
Engineer Ehsan,, Bahman; Lic. No.: S1708 3440 OAKMONT VIEW DR      GLENDALE, CA 91208

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/30/2022 Not Ready for Inspection PETER FOLLING
Deputy Drilled-In Anchors 4/25/2022 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 5/5/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 6/2/2022 Partial Approval PETER FOLLING
Insulation 6/2/2022 Partial Approval PETER FOLLING
PLUMBING-Rough 6/8/2022 Approved SEAN HAUPT
Wood Frame 6/14/2022 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Approved VINCENT HANLEY
Green Building Rough 9/12/2022 Not Ready for Inspection VINCENT HANLEY
MERV13>=Rough 9/12/2022 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 2/16/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Approved VINCENT HANLEY
HVAC-Rough 2/16/2023 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 2/16/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/22/2023 Approved VINCENT HANLEY
Green Building Rough 2/22/2023 Approved VINCENT HANLEY
HVAC-Rough 2/22/2023 Approved VINCENT HANLEY
MERV13>=Rough 2/22/2023 Approved VINCENT HANLEY
Insulation 3/6/2023 Approved VINCENT HANLEY
Special/Order Compliance 3/6/2023 Partial Inspection JUSTIN HAWLEY
Drywall Nailing 3/16/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/22/2023 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 4/4/2023 Approved VINCENT HANLEY
Shower Pan 4/4/2023 Approved VINCENT HANLEY
PLUMBING-Final 10/31/2023 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Not Ready VINCENT HANLEY
Final 4/2/2024 Corrections Issued VINCENT HANLEY
Green Building Final 4/2/2024 Approved VINCENT HANLEY
MERV13>=Final 4/2/2024 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/2/2024 SGSOV Approved VINCENT HANLEY
Smoke Detectors 4/2/2024 Approved VINCENT HANLEY
Final 6/4/2024 Corrections Issued THOMAS FINNILA
MERV13>=Final 6/4/2024 Approved THOMAS FINNILA
Final 12/20/2024 Corrections Issued THOMAS FINNILA
Final 1/24/2025 Not Ready for Inspection JOHN COLEMAN
Final 2/3/2025 Not Ready for Inspection JOHN COLEMAN
Final 2/28/2025 Corrections Issued JOHN COLEMAN
Final 5/8/2025 Not Ready for Inspection THOMAS FINNILA
Final 9/24/2025 Not Ready for Inspection SEAN WIRCH
Final 12/4/2025 OK to Issue CofO SEAN WIRCH