7716 N AURA AVE 91335
Certificate Information: 7716 N AURA AVE 91335
- Application / Permit
- 21014-30000-04901
- Plan Check / Job No.
- B21WL04303
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Mater bedoom addition to an (e) S.F.R.
- Permit Issued
- Issued on 12/1/2021
- Issuing Office
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2021 | RICHARD GARCIA |
| Corrections Issued | 10/2/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 11/2/2021 | RICHARD GARCIA |
| Plan Check Approved | 11/15/2021 | KHUONG TRUONG |
| Building Plans Picked Up | 11/16/2021 | APPLICANT |
| Issued | 12/1/2021 | APPLICANT |
| CofO in Progress | 3/29/2023 | JEFFREY BULL |
| Permit Finaled | 4/18/2023 | JOHN JANSON |
| CofO Issued | 4/18/2023 | JOHN JANSON |
| Permit Finaled | 4/18/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/26/2021 | CARLOS AGUILERA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/15/2022 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/22/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/22/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/22/2022 | Partial Approval | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 6/15/2022 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 6/17/2022 | Partial Approval | JEFFREY BULL |
| Green Building Rough | 6/17/2022 | Not Ready for Inspection | JEFFREY BULL |
| BUILDING-Rough-Frame | 8/23/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 8/23/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 8/23/2022 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 8/23/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 8/23/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/23/2022 | Approved | JEFFREY PARD |
| Drywall Nailing | 10/4/2022 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Approved | JEFFREY BULL |
| Insulation | 10/4/2022 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 10/13/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 3/28/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 3/28/2023 | Approved | JEFFREY BULL |
| Final | 3/28/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 3/28/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 3/28/2023 | Approved | JEFFREY BULL |
| HVAC-Final | 3/28/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 3/28/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 3/28/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 3/28/2023 | Approved | JEFFREY BULL |