951 N EMBURY ST 90272
Certificate Information: 951 N EMBURY ST 90272
- Application / Permit
- 21014-30000-04881
- Plan Check / Job No.
- B21WL04281
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2-story addition (2,185 sf) (to (e) single story SFD (1,044 sf) , add an att. 2-car garage (347 sf)
- Permit Issued
- Issued on 3/4/2022
- Issuing Office
- Current Status
- CofO Issued on 11/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | REZA HAGHIGHAT |
| Corrections Issued | 10/11/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 10/20/2021 | TARIK SAOUD |
| Plan Check Approved | 3/4/2022 | REZA HAGHIGHAT |
| Issued | 3/4/2022 | APPLICANT |
| Building Plans Picked Up | 6/16/2022 | APPLICANT |
| CofO in Progress | 11/2/2023 | OGANES TARAKHCHYAN |
| Permit Finaled | 11/9/2023 | DANIEL ORRANTE |
| CofO Issued | 11/9/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/9/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 11/1/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2021 | DINAH GARIN |
| Sewer availability | Cleared | 11/2/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 12/9/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/22/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 1/19/2022 | GILBERT URREA |
| Trees in Parkway | Cleared | 2/2/2022 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 3/4/2022 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 3/4/2022 | REZA HAGHIGHAT |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/7/2022 | No Access for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 10/19/2022 | Partial Approval | KEVIN SARGSYAN |
| Pre-Inspection | 10/26/2022 | Partial Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/4/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/4/2022 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/17/2022 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/17/2022 | Approved | KEVIN SARGSYAN |
| Deputy Wood Construction | 11/30/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 12/9/2022 | Approved | KEVIN SARGSYAN |
| Deputy Wood Construction | 12/21/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Wood Construction | 12/28/2022 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 12/29/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2023 | No Access for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/11/2023 | No Access for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2023 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/13/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 1/24/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/24/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 1/25/2023 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 2/9/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Shower Pan | 2/9/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 2/16/2023 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 2/16/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 4/4/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/11/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 4/11/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/11/2023 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/14/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 4/14/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/25/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/5/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/9/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/11/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/24/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Gas Test | 9/8/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 9/8/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Final | 9/8/2023 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/8/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 9/19/2023 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 9/19/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 9/19/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 9/19/2023 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 9/22/2023 | Approved | KENNETH NAGLE |
| Final | 10/27/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 11/1/2023 | OK to Issue CofO | OGANES TARAKHCHYAN |