6406 W 84TH ST 90045
Certificate Information: 6406 W 84TH ST 90045
- Application / Permit
- 21014-30000-04815
- Plan Check / Job No.
- B21WL04243
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story addition and major remodel to (e) 1-story S.F.D.
- Permit Issued
- Issued on 6/3/2022
- Issuing Office
- Current Status
- CofO Issued on 9/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2021 | KAVIAN REFAHI |
| Corrections Issued | 9/29/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 3/11/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 3/24/2022 | MARJAN SHENASI |
| Applicant returned to address corrections | 5/6/2022 | EDWIN ESPIN |
| Plan Check Approved | 5/24/2022 | JASON JANGADA |
| Building Plans Picked Up | 5/25/2022 | APPLICANT |
| Issued | 6/3/2022 | APPLICANT |
| CofO in Progress | 9/6/2023 | HERBERT GIRON |
| Permit Finaled | 9/9/2023 | DANIEL ORRANTE |
| CofO Issued | 9/9/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 11/30/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2021 | DINAH GARIN |
| Sewer availability | Cleared | 12/2/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 3/22/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/25/2022 | SAUL GARCIA |
| Trees in Parkway | Cleared | 4/29/2022 | ADALBERTO VERA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Contreras Kevin; Lic. No.: 1073207-B | 11046 ODELL AVE SUNLAND, CA 91040 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/6/2022 | Conditional Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 7/6/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/12/2022 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/17/2022 | Conditional Approval | HERBERT GIRON |
| Insulation | 8/17/2022 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 8/17/2022 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 8/31/2022 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 10/20/2022 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 10/20/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 10/20/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 11/1/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 11/1/2022 | Conditional Approval | HERBERT GIRON |
| PLUMBING-Rough | 11/1/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 11/14/2022 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 11/14/2022 | Approved | HERBERT GIRON |
| HVAC-Rough | 11/14/2022 | Approved | HERBERT GIRON |
| Special/Order Compliance | 11/14/2022 | Corrections Issued | HERBERT GIRON |
| Deputy Wood Construction | 11/21/2022 | Conditional Approval | HERBERT GIRON |
| Final | 11/21/2022 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/21/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 11/21/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/2/2022 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 12/2/2022 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 12/2/2022 | Not Ready for Inspection | HERBERT GIRON |
| Wood Frame | 12/2/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/12/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 12/12/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 12/12/2022 | Partial Approval | HERBERT GIRON |
| Verify Sprinkler Sign Off | 12/12/2022 | Approved | HERBERT GIRON |
| Green Building Final | 12/16/2022 | Not Ready for Inspection | HERBERT GIRON |
| Insulation | 12/16/2022 | Corrections Issued | HERBERT GIRON |
| Insulation | 12/20/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 12/30/2022 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 2/15/2023 | Approved | HERBERT GIRON |
| Shower Pan | 2/15/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 5/9/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 5/9/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 5/18/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 5/18/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 5/25/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 5/25/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 5/30/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 5/30/2023 | Corrections Issued | HERBERT GIRON |
| Final | 6/1/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 6/1/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 6/1/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Approved | HERBERT GIRON |
| Final | 6/8/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 6/8/2023 | Approved | HERBERT GIRON |
| Smoke Detectors | 6/8/2023 | Approved | HERBERT GIRON |
| Final | 9/5/2023 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 9/5/2023 | Approved | HERBERT GIRON |