8314 S ALTAVAN AVE 90045

Certificate Information: 8314 S ALTAVAN AVE 90045

Application / Permit
21014-30000-04701
Plan Check / Job No.
B21WL04123
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel and addition to SFD.
Permit Issued
Issued on 10/6/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 MANUEL GARCIA
Corrections Issued 10/21/2021 MANUEL GARCIA
Quality Review Completed 11/1/2021 TARIK SAOUD
Applicant returned to address corrections 12/16/2021 MANUEL GARCIA
Applicant returned to address corrections 3/4/2022 YASHAR EMAMI
Applicant returned to address corrections 3/7/2022 YASHAR EMAMI
Applicant returned to address corrections 4/15/2022 YASHAR EMAMI
Applicant returned to address corrections 6/1/2022 YASHAR EMAMI
Applicant returned to address corrections 7/8/2022 YASHAR EMAMI
Applicant returned to address corrections 8/22/2022 YASHAR EMAMI
Building Plans Picked Up 8/24/2022 APPLICANT
Applicant returned to address corrections 9/20/2022 YASHAR EMAMI
Plan Check Approved 9/22/2022 YASHAR EMAMI
Issued 10/6/2022 APPLICANT
CofO in Progress 1/26/2024 BOBBY KEY
Permit Finaled 1/30/2024 DANIEL ORRANTE
CofO Issued 1/30/2024 DANIEL ORRANTE
Permit Finaled 1/30/2024 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 12/7/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/9/2021 DINAH GARIN
Sewer availability Cleared 12/9/2021 DINAH GARIN
Certificate of Compliance Cleared 2/8/2022 MARC WOERSCHING
ZA Case Cleared 2/9/2022 LAUREN PADICK
Low Impact Development Cleared 5/6/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/12/2022 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/22/2022 Conditional Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 12/27/2022 Approved BOBBY KEY
Footing/Foundation/Slab 12/27/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/13/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 2/13/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 2/16/2023 Partial Approval BOBBY KEY
Pre-Inspection 4/18/2023 Partial Inspection BOBBY KEY
ELECTRICAL-Rough 5/1/2023 Corrections Issued BOBBY KEY
Final 5/4/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/4/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 5/4/2023 Conditional Approval BOBBY KEY
Interior/Exterior Lathing 5/24/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 5/30/2023 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 6/1/2023 No Access for Inspection BOBBY KEY
HVAC-Rough 6/1/2023 No Access for Inspection BOBBY KEY
PLUMBING-Rough 6/1/2023 No Access for Inspection BOBBY KEY
BUILDING-Rough-Frame 6/6/2023 Approved BOBBY KEY
ELECTRICAL-Rough 6/6/2023 Conditional Approval BOBBY KEY
Green Building Rough 6/6/2023 Approved BOBBY KEY
HVAC-Rough 6/6/2023 Approved BOBBY KEY
PLUMBING-Rough 6/6/2023 Approved BOBBY KEY
Shower Pan 6/21/2023 Approved BOBBY KEY
ELECTRICAL-Rough 6/29/2023 Not Ready for Inspection BOBBY KEY
Insulation 6/29/2023 Approved BOBBY KEY
Interior/Exterior Lathing 7/7/2023 Approved BOBBY KEY
ELECTRICAL-Rough 7/14/2023 Approved DAVID FEILER
Drywall Nailing 7/24/2023 Approved BOBBY KEY
Verify Sprinkler Sign Off 8/8/2023 Approved BOBBY KEY
ELECTRICAL-Final 10/23/2023 Corrections Issued BOBBY KEY
HVAC-Final 10/23/2023 Corrections Issued BOBBY KEY
PLUMBING-Final 10/23/2023 Corrections Issued BOBBY KEY
Sewer 10/31/2023 Approved BOBBY KEY
ELECTRICAL-Final 11/8/2023 Corrections Issued BOBBY KEY
Final 11/8/2023 Corrections Issued BOBBY KEY
HVAC-Final 11/8/2023 Corrections Issued BOBBY KEY
PLUMBING-Final 11/8/2023 Corrections Issued BOBBY KEY
Smoke Detectors 11/8/2023 Approved BOBBY KEY
ELECTRICAL-Final 11/14/2023 Not Ready for Inspection BOBBY KEY
HVAC-Final 11/14/2023 Approved BOBBY KEY
PLUMBING-Final 11/14/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 11/21/2023 Approved BOBBY KEY
ELECTRICAL-Final 11/21/2023 Approved BOBBY KEY
Final 11/21/2023 Corrections Issued BOBBY KEY
Gas Test 11/21/2023 Approved BOBBY KEY
Green Building Final 11/21/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Approved BOBBY KEY
Final 1/22/2024 No Access for Inspection JESUS RODRIGUEZ
Final 1/26/2024 OK to Issue CofO BOBBY KEY
Service/Power Release 1/26/2024 Approved BOBBY KEY