518 E SUNSET AVE 90291
Certificate Information: 518 E SUNSET AVE 90291
- Application / Permit
- 21014-30000-04694
- Plan Check / Job No.
- B21WL04098
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- add new 2 bedrooms and bathrooms and 493 sf at first and second floor of the (e) single family residence.
- Permit Issued
- Issued on 2/12/2022
- Issuing Office
- Current Status
- CofO Issued on 6/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 10/13/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 10/20/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 12/1/2021 | FELIPE HERNANDEZ |
| Building Plans Picked Up | 12/2/2021 | APPLICANT |
| Applicant returned to address corrections | 12/22/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 1/10/2022 | FELIPE HERNANDEZ |
| Issued | 2/12/2022 | APPLICANT |
| CofO in Progress | 6/14/2024 | HERBERT GIRON |
| Permit Finaled | 6/17/2024 | DANIEL ORRANTE |
| CofO Issued | 6/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 10/27/2021 | MAXFIELD VERMY |
| ZA Case | Cleared | 10/27/2021 | MAXFIELD VERMY |
| Specific Plan | Cleared | 11/12/2021 | BINDU KANNAN |
| Coastal Zone | Cleared | 12/8/2021 | MAXFIELD VERMY |
| Roof/Waste drainage to street | Cleared | 12/14/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Towers,, Kevin Mitchell; Lic. No.: S6625 | 6121 IROQUOIS RD WESTMINSTER, CA 92683 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/28/2022 | No Access for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 3/7/2022 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 3/7/2022 | Approved | DAVID FEILER |
| METHANE-Barrier | 3/7/2022 | Approved | DAVID FEILER |
| METHANE-Subgrade | 3/7/2022 | Approved | DAVID FEILER |
| Underground Mechanical | 3/7/2022 | Partial Approval | DAVID FEILER |
| Deputy Wood Construction | 8/17/2022 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2022 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Partial Approval | DAVID FEILER |
| Gas Test | 11/4/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 11/4/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 11/4/2022 | Corrections Issued | DAVID FEILER |
| Underground Mechanical | 11/4/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 11/15/2022 | Approved | DAVID FEILER |
| PLUMBING-Rough | 11/15/2022 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 12/16/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | EVAN COOPER |
| Green Building Rough | 12/16/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 12/16/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 1/11/2023 | Approved | EVAN COOPER |
| Green Building Rough | 1/11/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/11/2023 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 1/11/2023 | Approved | EVAN COOPER |
| Insulation | 1/18/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 1/26/2023 | Approved | EVAN COOPER |
| Service/Power Release | 2/10/2023 | Approved | EVAN COOPER |
| Deputy Drilled-In Anchors | 11/13/2023 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Final | 5/31/2024 | Not Ready for Inspection | HERBERT GIRON |
| Final | 5/31/2024 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Final | 5/31/2024 | Approved | HERBERT GIRON |
| HVAC-Final | 5/31/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 5/31/2024 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 6/14/2024 | Approved | HERBERT GIRON |
| Final | 6/14/2024 | OK to Issue CofO | HERBERT GIRON |
| Gas Test | 6/14/2024 | Approved | HERBERT GIRON |
| PLUMBING-Final | 6/14/2024 | Approved | HERBERT GIRON |
| Smoke Detectors | 6/14/2024 | Approved | HERBERT GIRON |