6422 W 87TH PL 90045

Certificate Information: 6422 W 87TH PL 90045

Application / Permit
21014-30000-04662
Plan Check / Job No.
B21WL04088
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
Full Bathroom for the (E) Pool Accessed from Outside only and Storage Room Addition to the rear of (E) Detached Garage. "COMPLY WITH DEPARTMENT ORDER effective date 04/06/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 7/15/2022
Issuing Office
Current Status
Issued on 7/15/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/15/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 JAHANSHAH POURHASSAN
Corrections Issued 9/16/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 4/28/2022 JASON JANGADA
Applicant returned to address corrections 5/27/2022 JASON JANGADA
Plan Check Approved 7/1/2022 DAVID CASTILLO
Issued 7/15/2022 APPLICANT
Building Plans Picked Up 7/21/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/20/2022 JENSON LEE
Sewer availability Cleared 4/20/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 5/4/2022 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/26/2022 Not Ready for Inspection JOHN MATTILLO
Drywall Nailing 10/26/2022 Not Ready for Inspection JOHN MATTILLO
Final 10/26/2022 Not Ready for Inspection JOHN MATTILLO
Footing/Foundation/Slab 10/26/2022 Not Ready for Inspection JOHN MATTILLO
Green Building Final 10/26/2022 Not Ready for Inspection JOHN MATTILLO
Green Building Rough 10/26/2022 Not Ready for Inspection JOHN MATTILLO
Smoke Detectors 10/26/2022 Not Ready for Inspection JOHN MATTILLO
Final 3/15/2023 OK to Expire Permit ANDREW BEELI