6422 W 87TH PL 90045
Certificate Information: 6422 W 87TH PL 90045
- Application / Permit
- 21014-30000-04662
- Plan Check / Job No.
- B21WL04088
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- Full Bathroom for the (E) Pool Accessed from Outside only and Storage Room Addition to the rear of (E) Detached Garage. "COMPLY WITH DEPARTMENT ORDER effective date 04/06/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 7/15/2022
- Issuing Office
- Current Status
- Issued on 7/15/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 9/16/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 4/28/2022 | JASON JANGADA |
| Applicant returned to address corrections | 5/27/2022 | JASON JANGADA |
| Plan Check Approved | 7/1/2022 | DAVID CASTILLO |
| Issued | 7/15/2022 | APPLICANT |
| Building Plans Picked Up | 7/21/2022 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/20/2022 | JENSON LEE |
| Sewer availability | Cleared | 4/20/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2022 | JENSON LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/26/2022 | Not Ready for Inspection | JOHN MATTILLO |
| Drywall Nailing | 10/26/2022 | Not Ready for Inspection | JOHN MATTILLO |
| Final | 10/26/2022 | Not Ready for Inspection | JOHN MATTILLO |
| Footing/Foundation/Slab | 10/26/2022 | Not Ready for Inspection | JOHN MATTILLO |
| Green Building Final | 10/26/2022 | Not Ready for Inspection | JOHN MATTILLO |
| Green Building Rough | 10/26/2022 | Not Ready for Inspection | JOHN MATTILLO |
| Smoke Detectors | 10/26/2022 | Not Ready for Inspection | JOHN MATTILLO |
| Final | 3/15/2023 | OK to Expire Permit | ANDREW BEELI |