1215 N ISABEL ST 90065
Certificate Information: 1215 N ISABEL ST 90065
- Application / Permit
- 21014-30000-04655
- Plan Check / Job No.
- B21WL04079
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Single story addition and remodel existing 1-story single family dwelling.
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- CofO Issued on 11/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2021 | KAVIAN REFAHI |
| Corrections Issued | 9/18/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/26/2021 | MARJAN SHENASI |
| Plan Check Approved | 11/30/2021 | MARJAN SHENASI |
| Issued | 3/18/2022 | APPLICANT |
| Building Plans Picked Up | 4/19/2022 | APPLICANT |
| CofO in Progress | 11/8/2022 | OSVALDO PARAMO |
| CofO in Progress | 11/8/2022 | OSVALDO PARAMO |
| Permit Finaled | 11/12/2022 | DEROLD HAUFF |
| CofO Issued | 11/12/2022 | DEROLD HAUFF |
| Permit Finaled | 11/12/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/22/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2021 | WALLIE JONG |
| Miscellaneous | Cleared | 9/27/2021 | KENTON TRINH |
| Specific Plan | Cleared | 10/8/2021 | NASHYA JENSEN |
| Grading Pre-Inspection | Cleared | 10/26/2021 | KAVIAN REFAHI |
Contact Information
| Architect | Nguyen,, Timothy; Lic. No.: C35111 | 20 SALTAIRE LAGUNA NIGUEL, CA 92677 |
| Contractor | Owner-Builder | , |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | PO BOX 8840 POMONA, CA 91701 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/11/2022 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/11/2022 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/20/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/28/2022 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Approved | OSVALDO PARAMO |
| Wood Frame | 5/20/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/16/2022 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 6/16/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 6/16/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/20/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/20/2022 | Approved | OSVALDO PARAMO |
| Green Building Rough | 6/20/2022 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 6/20/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 6/20/2022 | Partial Approval | OSVALDO PARAMO |
| Insulation | 6/21/2022 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 6/24/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 6/24/2022 | Approved | OSVALDO PARAMO |
| Shower Pan | 6/30/2022 | Approved | OSVALDO PARAMO |
| Final | 9/26/2022 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 9/26/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 9/26/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 9/26/2022 | Approved | OSVALDO PARAMO |
| Final | 10/11/2022 | Corrections Issued | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Approved | OSVALDO PARAMO |
| Final | 11/4/2022 | OK to Issue CofO | OSVALDO PARAMO |