2134 S GREENFIELD AVE 90025
Certificate Information: 2134 S GREENFIELD AVE 90025
- Application / Permit
- 21014-30000-04612
- Plan Check / Job No.
- B21WL04048
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1st and 2nd Floor Addition with Remodel and (N) Garage Attached to (E) 1-Story S.F.D
- Permit Issued
- Issued on 2/6/2023
- Issuing Office
- Current Status
- CofO Issued on 8/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | DAVID CASTILLO |
| Corrections Issued | 10/19/2021 | DAVID CASTILLO |
| Quality Review Completed | 10/27/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 7/1/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/30/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 9/8/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 9/13/2022 | APPLICANT |
| Applicant returned to address corrections | 12/19/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 1/6/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 1/18/2023 | DAVID CASTILLO |
| Plan Check Approved | 2/3/2023 | DAVID CASTILLO |
| Issued | 2/6/2023 | APPLICANT |
| CofO in Progress | 8/5/2024 | KIRK SANDERS |
| Permit Finaled | 8/8/2024 | DANIEL ORRANTE |
| CofO Issued | 8/8/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/8/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2022 | DINAH GARIN |
| Sewer availability | Cleared | 6/17/2022 | DINAH GARIN |
| Low Impact Development | Cleared | 12/8/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 12/12/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 12/19/2022 | DAVID CASTILLO |
| Permit | Cleared | 12/24/2022 | SAUL GARCIA |
| Trees in Parkway | Cleared | 1/11/2023 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/2/2023 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 5/2/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/15/2023 | Corrections Issued | JEREMY TODD |
| ELECTRICAL-Rough | 5/15/2023 | Not Ready for Inspection | JEREMY TODD |
| Green Building Rough | 5/15/2023 | Not Ready for Inspection | JEREMY TODD |
| HVAC-Rough | 5/15/2023 | Not Ready for Inspection | JEREMY TODD |
| PLUMBING-Rough | 5/15/2023 | Partial Approval | JEREMY TODD |
| Underground Mechanical | 5/15/2023 | Not Ready for Inspection | JEREMY TODD |
| Wood Frame | 5/15/2023 | Not Ready for Inspection | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Partial Approval | JEREMY TODD |
| PLUMBING-Rough | 7/5/2023 | Not Ready for Inspection | JEREMY TODD |
| Deputy Wood Construction | 7/6/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 7/6/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 8/16/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Rough | 8/16/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/16/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Wood Frame | 8/16/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 8/19/2023 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Rough | 9/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 9/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/19/2023 | Approved | CARLOS MATAMOROS |
| Wood Frame | 9/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | No Access for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/23/2023 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 10/23/2023 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 10/23/2023 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 10/23/2023 | Corrections Issued | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 10/23/2023 | Partial Approval | BEN MOLSTAD |
| ELECTRICAL-Rough | 10/25/2023 | Corrections Issued | BEN MOLSTAD |
| HVAC-Rough | 10/25/2023 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/27/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/27/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 10/27/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 10/27/2023 | Corrections Issued | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/27/2023 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 10/27/2023 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 10/27/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 11/2/2023 | Corrections Issued | MICHAEL PELHAM |
| Insulation | 11/7/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Drywall Nailing | 11/13/2023 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Rough | 11/13/2023 | Approved | MICHAEL PELHAM |
| Insulation | 11/13/2023 | Approved | MICHAEL PELHAM |
| Special/Order Compliance | 11/13/2023 | Corrections Issued | MICHAEL PELHAM |
| Interior/Exterior Lathing | 11/20/2023 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 12/22/2023 | SGSOV Not Ready | STEPHANIE SWANSON |
| Drywall Nailing | 4/9/2024 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 4/9/2024 | Not Ready for Inspection | JESUS PINEDA |
| Final | 4/9/2024 | Not Ready for Inspection | JESUS PINEDA |
| Gas Test | 4/9/2024 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Final | 4/9/2024 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Final | 4/9/2024 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Final | 4/9/2024 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV Not Ready | JESUS PINEDA |
| Service/Power Release | 4/9/2024 | Not Ready for Inspection | JESUS PINEDA |
| Smoke Detectors | 4/9/2024 | Not Ready for Inspection | JESUS PINEDA |
| Drywall Nailing | 5/10/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 5/10/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 5/10/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 5/10/2024 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 5/10/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 5/14/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 5/14/2024 | Not Ready for Inspection | KIRK SANDERS |
| Service/Power Release | 5/14/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 5/21/2024 | Corrections Issued | KIRK SANDERS |
| Final | 5/21/2024 | Not Ready for Inspection | KIRK SANDERS |
| Gas Test | 5/21/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 5/21/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 5/21/2024 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 5/21/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 5/23/2024 | Corrections Issued | KIRK SANDERS |
| Gas Test | 5/23/2024 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Final | 5/23/2024 | Approved | KIRK SANDERS |
| HVAC-Final | 5/23/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 5/23/2024 | Approved | KIRK SANDERS |
| Service/Power Release | 5/23/2024 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 5/23/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 5/31/2024 | No Access for Inspection | KIRK SANDERS |
| Gas Test | 5/31/2024 | No Access for Inspection | KIRK SANDERS |
| HVAC-Final | 5/31/2024 | No Access for Inspection | KIRK SANDERS |
| Service/Power Release | 5/31/2024 | No Access for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 6/6/2024 | Partial Approval | KIRK SANDERS |
| Gas Test | 6/6/2024 | Approved | KIRK SANDERS |
| HVAC-Final | 6/6/2024 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 6/6/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 6/13/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 6/13/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 6/13/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 7/1/2024 | No Access for Inspection | KIRK SANDERS |
| Final | 7/1/2024 | No Access for Inspection | KIRK SANDERS |
| HVAC-Final | 7/1/2024 | No Access for Inspection | KIRK SANDERS |
| PLUMBING-Final | 7/1/2024 | No Access for Inspection | KIRK SANDERS |
| Final | 7/8/2024 | Corrections Issued | KIRK SANDERS |
| Final | 8/2/2024 | OK to Issue CofO | KIRK SANDERS |