7912 S EL MANOR AVE 90045
Certificate Information: 7912 S EL MANOR AVE 90045
- Application / Permit
- 21014-30000-04597
- Plan Check / Job No.
- B21WL04030
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) single family dwelling and interior remodel . Per engineering design."COMPLY WITH DEPARTMENT ORDER effective date 10/01/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 931838.
- Permit Issued
- Issued on 12/3/2021
- Issuing Office
- Current Status
- CofO Issued on 5/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2021 | CHIHARU SUZUKI |
| Corrections Issued | 9/14/2021 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 10/26/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 10/28/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 11/3/2021 | JASON JANGADA |
| Plan Check Approved | 11/15/2021 | ALFREDO JARA |
| No Progress | 11/15/2021 | ALFREDO JARA |
| Plan Check Approved | 11/15/2021 | ALFREDO JARA |
| No Progress | 11/15/2021 | ALFREDO JARA |
| Plan Check Approved | 12/1/2021 | ALFREDO JARA |
| Issued | 12/3/2021 | APPLICANT |
| Building Plans Picked Up | 12/6/2021 | APPLICANT |
| CofO in Progress | 5/9/2022 | JOHN MATTILLO |
| CofO Issued | 5/25/2022 | BRUCE TODD |
| Permit Finaled | 5/25/2022 | BRUCE TODD |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/18/2021 | TAIMOUR TANAVOLI |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2021 | NIKTA MOUSAVI |
| Grading Pre-Inspection | Cleared | 11/3/2021 | HOOMAN HAJIZADEH |
| Roof/Waste drainage to street | Cleared | 11/5/2021 | SAUL GARCIA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Kook & Associates Construction Inc; Lic. No.: 820560-B | 14632 TUSTIN ST LOS ANGELES, CA 91403 |
| Engineer | Namdar,, Mansour Tom; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/7/2021 | Conditional Approval | MARIAN PODPORA |
| Footing/Foundation/Slab | 12/7/2021 | Conditional Approval | MARIAN PODPORA |
| Footing/Foundation/Slab | 12/15/2021 | Corrections Issued | MARIAN PODPORA |
| Footing/Foundation/Slab | 12/17/2021 | Conditional Approval | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2021 | Partial Approval | JOHN MATTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2022 | Corrections Issued | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Conditional Approval | MARIAN PODPORA |
| HVAC-Rough | 2/3/2022 | Corrections Issued | MARIAN PODPORA |
| ELECTRICAL-Rough | 2/4/2022 | Corrections Issued | MARIAN PODPORA |
| PLUMBING-Rough | 2/4/2022 | Not Ready for Inspection | MARIAN PODPORA |
| BUILDING-Rough-Frame | 2/8/2022 | Approved | MARIAN PODPORA |
| ELECTRICAL-Rough | 2/8/2022 | Partial Approval | MARIAN PODPORA |
| Gas Test | 2/8/2022 | Partial Approval | MARIAN PODPORA |
| Green Building Rough | 2/8/2022 | Approved | MARIAN PODPORA |
| PLUMBING-Rough | 2/8/2022 | Approved | MARIAN PODPORA |
| Sewer | 2/8/2022 | Not Ready for Inspection | MARIAN PODPORA |
| Shower Pan | 2/14/2022 | Approved | JOHN MATTILLO |
| Interior/Exterior Lathing | 2/22/2022 | Approved | JOHN MATTILLO |
| Insulation | 2/25/2022 | Conditional Approval | MARIAN PODPORA |
| Drywall Nailing | 3/1/2022 | Corrections Issued | MARIAN PODPORA |
| Interior/Exterior Lathing | 3/2/2022 | Conditional Approval | MARIAN PODPORA |
| PLUMBING-Rough | 3/15/2022 | Partial Approval | MARIAN PODPORA |
| Sewer | 3/15/2022 | Conditional Approval | MARIAN PODPORA |
| Drywall Nailing | 5/6/2022 | Approved | JOHN MATTILLO |
| Final | 5/6/2022 | Conditional Approval | JOHN MATTILLO |
| Footing/Foundation/Slab | 5/6/2022 | Approved | JOHN MATTILLO |
| Green Building Final | 5/6/2022 | Approved | JOHN MATTILLO |
| SGSOV-Seismic Gas S/O Valve | 5/6/2022 | SGSOV Approved | JOHN MATTILLO |
| Smoke Detectors | 5/6/2022 | Approved | JOHN MATTILLO |
| Service/Power Release | 5/16/2022 | Approved | JOHN MATTILLO |