706 E MARR ST 90291

Certificate Information: 706 E MARR ST 90291

Application / Permit
21014-30000-04595
Plan Check / Job No.
B21WL04027
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 3.75' x 9.75 ON THE FIRST STORY AND AN IRREGULAR SECOND STORY ADDITION OF 15'8" x 25'2" AND A 9'4" x 12.75' ROOFTOP DECK OVER THE GARAGE, AND INTERIOR ALTERATION TO REVISE THE FIRST STORY FLOOR PLAN AND REMODELING THROUGHOUT.
Permit Issued
Issued on 12/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 ALFREDO JARA
Corrections Issued 9/21/2021 ALFREDO JARA
Applicant returned to address corrections 12/16/2021 ALFREDO JARA
Applicant returned to address corrections 3/21/2022 ALFREDO JARA
Applicant returned to address corrections 8/9/2022 ALFREDO JARA
Applicant returned to address corrections 11/7/2022 ALFREDO JARA
Building Plans Picked Up 11/7/2022 APPLICANT
Applicant returned to address corrections 12/1/2022 ALFREDO JARA
Plan Check Approved 12/23/2022 LUIS RINCON
Issued 12/23/2022 APPLICANT
CofO in Progress 11/8/2024 JESUS PINEDA
Permit Finaled 11/14/2024 RICHARD STEINBACH
CofO Issued 11/14/2024 RICHARD STEINBACH
Permit Finaled 11/14/2024 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/29/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 11/30/2021 ANTHONY MAINEZ
Coastal Zone Cleared 7/6/2022 DALIA MOKAYED
Miscellaneous Cleared 7/6/2022 DALIA MOKAYED
Miscellaneous Cleared 7/6/2022 DALIA MOKAYED
Specific Plan Cleared 7/25/2022 IRA BROWN
ZI Cleared 7/25/2022 IRA BROWN

Contact Information

Architect Whitten,, Charles Alexander; Lic. No.: C30241 10716 ESTHER AVE      LOS ANGELES, CA 90064
Contractor Owner-Builder       ,
Engineer Chikhale,, Jonathan William; Lic. No.: C78893 2820 MILITARY AVENUE      LOS ANGELES, CA 90064

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/21/2023 Approved EVAN COOPER
Pre-Inspection 3/13/2023 Approved EVAN COOPER
Deputy Drilled-In Anchors 4/4/2023 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Final 4/5/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 4/5/2023 Conditional Approval JESUS RODRIGUEZ
METHANE-Barrier 4/5/2023 Approved JESUS RODRIGUEZ
METHANE-Subgrade 4/5/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/14/2023 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/20/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 7/20/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 9/27/2023 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 9/27/2023 Approved TEMISTOCLES CAAL
HVAC-Rough 12/4/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/4/2023 Approved JESUS RODRIGUEZ
Sewer 12/4/2023 Approved JESUS RODRIGUEZ
Underground Mechanical 12/4/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/20/2023 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 12/20/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 1/19/2024 Conditional Approval JESUS RODRIGUEZ
Green Building Rough 1/19/2024 Approved JESUS RODRIGUEZ
Insulation 1/19/2024 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 1/19/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 2/2/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/22/2024 Approved HERBERT GIRON
Shower Pan 2/22/2024 Approved HERBERT GIRON
Gas Test 6/18/2024 Approved TEMISTOCLES CAAL
Pre-Inspection 6/18/2024 Partial Inspection TEMISTOCLES CAAL
PLUMBING-Final 8/7/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 8/8/2024 Corrections Issued HERBERT GIRON
HVAC-Final 8/9/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 8/9/2024 Approved HERBERT GIRON
ELECTRICAL-Final 8/12/2024 Approved JESUS RODRIGUEZ
Service/Power Release 8/12/2024 Approved JESUS RODRIGUEZ
HVAC-Final 8/16/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/7/2024 Approved JESUS PINEDA
Final 11/7/2024 OK to Issue CofO JESUS PINEDA
Green Building Final 11/7/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 11/7/2024 SGSOV Approved JESUS PINEDA
Smoke Detectors 11/7/2024 Approved JESUS PINEDA