8000 N MAESTRO AVE 91304

Certificate Information: 8000 N MAESTRO AVE 91304

Application / Permit
21014-30000-04592
Plan Check / Job No.
B21WL04019
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 story addition to (e) 1-story S.F.R. + interior remodel and patio cover addition
Permit Issued
Issued on 4/13/2022
Issuing Office
Current Status
CofO Issued on 3/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2021 APPLICANT
Assigned to Plan Check Engineer 9/13/2021 MANUEL GARCIA
Corrections Issued 9/13/2021 MANUEL GARCIA
Applicant returned to address corrections 3/23/2022 JASON JANGADA
Building Plans Picked Up 3/25/2022 APPLICANT
Plan Check Approved 4/4/2022 EDWIN ESPIN
Issued 4/13/2022 APPLICANT
CofO in Progress 3/13/2023 CHRIS CHRISTENSEN
CofO Issued 3/13/2023 JOHN JANSON
Permit Finaled 3/13/2023 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/26/2022 VASIL MIHALEV
Low Impact Development Cleared 3/10/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/14/2022 CARLOS AGUILERA
Sewer availability Cleared 3/14/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/15/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Song,, Zhenyu Michael; Lic. No.: S5266 12631 IMPERIAL HWY F-230      SANTA FE SPRINGS, CA 90670

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/18/2022 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/23/2022 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/26/2022 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 7/25/2022 Approved CHRIS CHRISTENSEN
Wood Frame 7/25/2022 Approved CHRIS CHRISTENSEN
Insulation 8/2/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 8/2/2022 Partial Approval JESUS PINEDA
Shower Pan 8/2/2022 Approved JESUS PINEDA
Drywall Nailing 8/9/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 8/9/2022 Approved JESUS PINEDA
BUILDING-Rough-Frame 11/22/2022 Approved CHRIS CHRISTENSEN
Final 11/22/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 11/22/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Rough 11/22/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 11/22/2022 Approved CHRIS CHRISTENSEN
Final 2/16/2023 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 2/16/2023 Approved CHRIS CHRISTENSEN