420 S BRISTOL AVE 90049
Certificate Information: 420 S BRISTOL AVE 90049
- Application / Permit
- 21014-30000-04576
- Plan Check / Job No.
- B21WL03992
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- remodel & addition to existing S.F.D
- Permit Issued
- Issued on 1/24/2022
- Issuing Office
- Current Status
- Issued on 1/24/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | KHUONG TRUONG |
| Corrections Issued | 10/3/2021 | KHUONG TRUONG |
| Quality Review Completed | 10/15/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 12/7/2021 | KHUONG TRUONG |
| Applicant returned to address corrections | 12/21/2021 | KHUONG TRUONG |
| Plan Check Approved | 1/14/2022 | KHUONG TRUONG |
| Issued | 1/24/2022 | APPLICANT |
| Building Plans Picked Up | 1/26/2022 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 10/4/2021 | Yasaman Shayesteh |
| Miscellaneous | Cleared | 11/3/2021 | RAYMOND MUGAMBWA |
| ZA Case | Cleared | 11/3/2021 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2021 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 11/5/2021 | NIKTA MOUSAVI |
| Specific Plan | Cleared | 11/15/2021 | VALERIA CEJA |
| Grading Pre-Inspection | Cleared | 12/7/2021 | KHUONG TRUONG |
| Low Impact Development | Cleared | 1/3/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 1/7/2022 | NIKTA MOUSAVI |
Contact Information
| Architect | Zahabian,, Philip; Lic. No.: C23813 | 5237 NEWCASTLE AVE #307 ENCINO, CA 91316 |
| Contractor | Bar Design And Construction Inc; Lic. No.: 786816-B | 11009 1/2 HESBY ST NORTH HOLLYWOOD, CA 91601 |
| Engineer | Eden,, Joseph Taki; Lic. No.: C39955 | 14412 FRIAR ST VAN NUYS, CA 91401 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/25/2022 | Corrections Issued | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/27/2022 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 5/23/2022 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 5/23/2022 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/25/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Partial Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 6/22/2022 | Conditional Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 7/29/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 8/3/2022 | Corrections Issued | PATRICK QUALEY |
| Footing/Foundation/Slab | 8/5/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 8/30/2022 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/6/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/8/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 2/27/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 7/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 8/4/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/4/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/28/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/28/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/6/2023 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/7/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/21/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/21/2024 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 3/18/2024 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 4/8/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 4/23/2024 | Corrections Issued | KENNETH NAGLE |
| Shower Pan | 4/25/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/2/2024 | Partial Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/8/2024 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 8/21/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 8/26/2025 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 9/22/2025 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 9/29/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 10/7/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 10/17/2025 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 10/17/2025 | Approved | HERBERT GIRON |
| PLUMBING-Final | 10/22/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 10/27/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 10/27/2025 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 10/27/2025 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 10/29/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 10/30/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 11/6/2025 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 11/21/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 11/21/2025 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 12/8/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 12/10/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 12/15/2025 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 12/18/2025 | Approved | HERBERT GIRON |
| Service/Power Release | 12/18/2025 | Approved | HERBERT GIRON |
| Final | 2/25/2026 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 2/25/2026 | Approved | HERBERT GIRON |
| Green Building Final | 2/25/2026 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 2/25/2026 | Approved | HERBERT GIRON |
| Final | 4/13/2026 | Not Ready for Inspection | DANIEL VERA |