207 N ARDEN BLVD 90004

Certificate Information: 207 N ARDEN BLVD 90004

Application / Permit
21014-30000-04574
Plan Check / Job No.
B21WL03989
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel of (e) SFD. Master bedroom and study addition. New rear wood deck.
Permit Issued
Issued on 4/22/2022
Issuing Office
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 RICHARD GARCIA
Corrections Issued 9/18/2021 RICHARD GARCIA
Building Plans Picked Up 11/24/2021 APPLICANT
Applicant returned to address corrections 12/22/2021 RICHARD GARCIA
Applicant returned to address corrections 12/28/2021 RICHARD GARCIA
Applicant returned to address corrections 4/9/2022 RICHARD GARCIA
Plan Check Approved 4/13/2022 RICHARD GARCIA
Issued 4/22/2022 APPLICANT
CofO in Progress 2/2/2024 RICHARD DOCKUS
Permit Finaled 2/22/2024 DEROLD HAUFF
CofO Issued 2/22/2024 DEROLD HAUFF
Permit Finaled 2/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/7/2021 WALLIE JONG
Sewer availability Cleared 12/7/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/8/2021 WALLIE JONG
HPOZ Cleared 3/23/2022 LYDIA CHAPMAN
ZI Cleared 3/23/2022 LYDIA CHAPMAN

Contact Information

Contractor G H Builders Inc; Lic. No.: 870657-B 16656 VENTURA BLVD STE 201      ENCINO, CA 914361928
Engineer Keshishian,, Anthony; Lic. No.: C89551 2654 RISA D      GLENDALE, CA 91208

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/27/2022 Approved ARTHUR SARGSYAN
METHANE-Barrier 4/27/2022 Approved ARTHUR SARGSYAN
METHANE-Subgrade 4/27/2022 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 7/12/2022 Not Ready for Inspection ADAM ESCOTO
ELECTRICAL-Rough 7/12/2022 Approved ADAM ESCOTO
Green Building Rough 7/12/2022 Not Ready for Inspection ADAM ESCOTO
HVAC-Rough 7/12/2022 Corrections Issued ADAM ESCOTO
METHANE-Rough 7/12/2022 Not Ready for Inspection ADAM ESCOTO
PLUMBING-Rough 7/12/2022 Not Ready for Inspection ADAM ESCOTO
Rough-Elec/Plmb/HVAC 7/15/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 7/18/2022 Conditional Approval ADAM ESCOTO
Green Building Rough 7/18/2022 Not Ready for Inspection ADAM ESCOTO
METHANE-Rough 7/18/2022 Approved ADAM ESCOTO
Insulation 8/18/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 8/18/2022 Approved MICHAEL LEWIS
Shower Pan 8/18/2022 Approved MICHAEL LEWIS
Drywall Nailing 8/29/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/19/2023 Approved RICHARD DOCKUS
Final 9/19/2023 Corrections Issued RICHARD DOCKUS
Green Building Final 9/19/2023 Approved RICHARD DOCKUS
Green Building Rough 9/19/2023 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 9/19/2023 Approved RICHARD DOCKUS
Final 11/13/2023 Not Ready for Inspection JOSEPH MCGARRY
Final 11/27/2023 Not Ready for Inspection RICHARD DOCKUS
Final 1/18/2024 OK to Issue CofO RICHARD DOCKUS