2991 N TIFFANY CIR 90077

Certificate Information: 2991 N TIFFANY CIR 90077

Application / Permit
21014-30000-04559
Plan Check / Job No.
B21WL03949
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel of an (e) S.F.D. w/ att. garage. Addition of 175 sf at rear of sfd and conversion of 375 sf above garage.
Permit Issued
Issued on 2/4/2022
Issuing Office
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 RICHARD GARCIA
Corrections Issued 9/28/2021 RICHARD GARCIA
Quality Review Completed 10/4/2021 TARIK SAOUD
Applicant returned to address corrections 11/19/2021 RICHARD GARCIA
Applicant returned to address corrections 1/14/2022 RICHARD GARCIA
Plan Check Approved 1/25/2022 RICHARD GARCIA
Building Plans Picked Up 1/27/2022 APPLICANT
Issued 2/4/2022 APPLICANT
CofO in Progress 8/6/2024 SEAN HAUPT
CofO Issued 8/14/2024 RICHARD STEINBACH
Permit Finaled 8/14/2024 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/14/2021 SAUL GARCIA
Sewer availability Cleared 10/14/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 10/15/2021 SAUL GARCIA
Specific Plan Cleared 10/22/2021 OLGA AYALA
ZI Cleared 10/22/2021 OLGA AYALA
GPI Written Notices Cleared 11/19/2021 RICHARD GARCIA
Grading Pre-Inspection Cleared 11/19/2021 RICHARD GARCIA
BHO/Hillside ordinance Cleared 11/30/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 11/30/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 11/30/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 11/30/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 11/30/2021 HISASHI KOBAYAKAWA

Contact Information

Contractor Owner-Builder       ,
Engineer Balshem,, Efim Bercovich; Lic. No.: C34313 1125 16TH ST UNIT 5      SANTA MONICA, CA 90403

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/7/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 7/7/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 7/7/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 8/17/2022 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 12/1/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 12/5/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Gas Test 1/24/2023 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 1/24/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 1/27/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 1/30/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 2/1/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 4/11/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 4/11/2023 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 4/12/2023 Approved STEPHANIE SWANSON
HVAC-Rough 4/12/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 4/12/2023 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 4/19/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 4/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 5/10/2023 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 5/10/2023 Approved CHRISTOPHER WILSON
Wood Frame 5/10/2023 Conditional Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/6/2023 Corrections Issued STEPHANIE SWANSON
Insulation 6/6/2023 Corrections Issued STEPHANIE SWANSON
Insulation 6/7/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 6/14/2023 Partial Approval BRENDAN LOONEY
Shower Pan 6/14/2023 Corrections Issued BRENDAN LOONEY
Special/Order Compliance 6/14/2023 Corrections Issued BRENDAN LOONEY
Special/Order Compliance 6/21/2023 Not Ready for Inspection BRENDAN LOONEY
Interior/Exterior Lathing 6/26/2023 Partial Approval BRENDAN LOONEY
Shower Pan 6/26/2023 Approved BRENDAN LOONEY
Drywall Nailing 7/26/2023 Approved BRENDAN LOONEY
Interior/Exterior Lathing 7/26/2023 Approved BRENDAN LOONEY
Gas Test 7/31/2023 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 7/31/2024 Approved SEAN HAUPT
Final 7/31/2024 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 7/31/2024 Approved SEAN HAUPT
Green Building Final 7/31/2024 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Approved SEAN HAUPT
Smoke Detectors 7/31/2024 Not Ready for Inspection SEAN HAUPT
Special/Order Compliance 7/31/2024 Approved SEAN HAUPT
Final 8/5/2024 OK to Issue CofO SEAN HAUPT
Smoke Detectors 8/5/2024 Approved SEAN HAUPT