2991 N TIFFANY CIR 90077
Certificate Information: 2991 N TIFFANY CIR 90077
- Application / Permit
- 21014-30000-04559
- Plan Check / Job No.
- B21WL03949
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel of an (e) S.F.D. w/ att. garage. Addition of 175 sf at rear of sfd and conversion of 375 sf above garage.
- Permit Issued
- Issued on 2/4/2022
- Issuing Office
- Current Status
- CofO Issued on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | RICHARD GARCIA |
| Corrections Issued | 9/28/2021 | RICHARD GARCIA |
| Quality Review Completed | 10/4/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 11/19/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 1/14/2022 | RICHARD GARCIA |
| Plan Check Approved | 1/25/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| Issued | 2/4/2022 | APPLICANT |
| CofO in Progress | 8/6/2024 | SEAN HAUPT |
| CofO Issued | 8/14/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/14/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/14/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 10/14/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2021 | SAUL GARCIA |
| Specific Plan | Cleared | 10/22/2021 | OLGA AYALA |
| ZI | Cleared | 10/22/2021 | OLGA AYALA |
| GPI Written Notices | Cleared | 11/19/2021 | RICHARD GARCIA |
| Grading Pre-Inspection | Cleared | 11/19/2021 | RICHARD GARCIA |
| BHO/Hillside ordinance | Cleared | 11/30/2021 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 11/30/2021 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 11/30/2021 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 11/30/2021 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 11/30/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Balshem,, Efim Bercovich; Lic. No.: C34313 | 1125 16TH ST UNIT 5 SANTA MONICA, CA 90403 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/7/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 7/7/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 7/7/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 8/17/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 12/1/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 12/5/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 1/24/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/24/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 1/27/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Deputy Reinf. Concrete | 1/30/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 2/1/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 4/11/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 4/11/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 4/12/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 4/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/12/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/19/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 4/19/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 5/10/2023 | Conditional Approval | CHRISTOPHER WILSON |
| Green Building Rough | 5/10/2023 | Approved | CHRISTOPHER WILSON |
| Wood Frame | 5/10/2023 | Conditional Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 6/6/2023 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 6/6/2023 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 6/7/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 6/14/2023 | Partial Approval | BRENDAN LOONEY |
| Shower Pan | 6/14/2023 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 6/14/2023 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 6/21/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 6/26/2023 | Partial Approval | BRENDAN LOONEY |
| Shower Pan | 6/26/2023 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 7/26/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 7/26/2023 | Approved | BRENDAN LOONEY |
| Gas Test | 7/31/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/31/2024 | Approved | SEAN HAUPT |
| Final | 7/31/2024 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 7/31/2024 | Approved | SEAN HAUPT |
| Green Building Final | 7/31/2024 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 7/31/2024 | Not Ready for Inspection | SEAN HAUPT |
| Special/Order Compliance | 7/31/2024 | Approved | SEAN HAUPT |
| Final | 8/5/2024 | OK to Issue CofO | SEAN HAUPT |
| Smoke Detectors | 8/5/2024 | Approved | SEAN HAUPT |