1039 S STANLEY AVE 90019

Certificate Information: 1039 S STANLEY AVE 90019

Application / Permit
21014-30000-04543
Plan Check / Job No.
B21WL03935
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF AND ADDITION TO (E) 1-STORY SFD.
Permit Issued
Issued on 11/8/2021
Issuing Office
Current Status
CofO Issued on 12/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 MARJAN SHENASI
Corrections Issued 9/11/2021 MARJAN SHENASI
Applicant returned to address corrections 10/13/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 10/20/2021 ALFREDO JARA
Plan Check Approved 11/2/2021 ALFREDO JARA
Issued 11/8/2021 APPLICANT
Building Plans Picked Up 11/9/2021 APPLICANT
CofO in Progress 11/1/2022 MICHAEL LEWIS
Permit Finaled 12/10/2022 DEROLD HAUFF
CofO Issued 12/10/2022 DEROLD HAUFF
Permit Finaled 12/10/2022 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 10/5/2021 RICHARD REASER
Sewer availability Cleared 10/13/2021 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 10/14/2021 CHRISTOPHER ROCHA
HPOZ Cleared 10/22/2021 CHRISTINA PARK
Roof/Waste drainage to street Cleared 10/26/2021 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/19/2021 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 11/24/2021 Approved ARTHUR SARGSYAN
Underground Mechanical 1/31/2022 Approved ARTHUR SARGSYAN
Insulation 2/7/2022 Approved ARTHUR SARGSYAN
Wood Frame 3/8/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 4/1/2022 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 4/1/2022 Corrections Issued CRAIG DAVIS
Green Building Rough 4/1/2022 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 4/1/2022 Not Ready for Inspection CRAIG DAVIS
METHANE-Rough 4/1/2022 Partial Inspection CRAIG DAVIS
PLUMBING-Rough 4/1/2022 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 4/13/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 4/13/2022 Approved ARTHUR SARGSYAN
Green Building Rough 4/13/2022 Approved ARTHUR SARGSYAN
HVAC-Rough 4/13/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 4/13/2022 Approved ARTHUR SARGSYAN
METHANE-Rough 4/13/2022 Approved ARTHUR SARGSYAN
PLUMBING-Rough 4/13/2022 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Approved ALIZAH MAYAGOITIA
Gas Test 4/19/2022 Approved ALIZAH MAYAGOITIA
Insulation 4/19/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 5/3/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 9/15/2022 Approved MICHAEL LEWIS
Final 9/15/2022 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 9/15/2022 Approved MICHAEL LEWIS
Green Building Final 9/15/2022 Approved MICHAEL LEWIS
METHANE-Barrier 9/15/2022 Approved MICHAEL LEWIS
METHANE-Subgrade 9/15/2022 Approved MICHAEL LEWIS
PLUMBING-Final 9/15/2022 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/15/2022 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 9/15/2022 Approved MICHAEL LEWIS
Final 10/31/2022 OK to Issue CofO MICHAEL LEWIS