1007 S TROTWOOD AVE 90732
Certificate Information: 1007 S TROTWOOD AVE 90732
- Application / Permit
- 21014-30000-04341
- Plan Check / Job No.
- B21WL03799
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Demo existing attached garage and rebuild and enlarge new garage. Remodel and addition to the rear of 1st floor. New 2nd floor master suite, bed, bath,wic
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Current Status
- Issued on 8/29/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | HOOMAN HAJIZADEH |
| Corrections Issued | 10/7/2021 | HOOMAN HAJIZADEH |
| Quality Review Completed | 10/20/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 4/18/2022 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 7/7/2022 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 7/19/2022 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 7/28/2022 | HOOMAN HAJIZADEH |
| Plan Check Approved | 8/24/2022 | HOOMAN HAJIZADEH |
| Issued | 8/29/2022 | APPLICANT |
| Building Plans Picked Up | 8/30/2022 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/19/2021 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 10/19/2021 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 10/19/2021 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 10/19/2021 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 10/19/2021 | ERIK BEASLEY |
| Construction within easement | Cleared | 4/6/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2022 | HUGO LOPEZ |
| Low Impact Development | Cleared | 7/6/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/6/2022 | HUGO LOPEZ |
| Sewer availability | Cleared | 7/6/2022 | HUGO LOPEZ |
| GPI Written Notices | Cleared | 7/7/2022 | HOOMAN HAJIZADEH |
| Grading Pre-Inspection | Cleared | 7/7/2022 | HOOMAN HAJIZADEH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abarquez,, Jose Munoz; Lic. No.: C51994 | 18 EL CORZO RANCHO SANTA MARGARITA, CA 92688 |
| Engineer | Doss,, Richard E; Lic. No.: C48987 | 30141 AGOURA RD 200 AGOURA HILLS, CA 91301 |
| Engineer | Reppuhn,, Nikolaus Yongbok; Lic. No.: C83924 | 1205 DUNNING WAY SAN DIMAS, CA 91773 |
| Engineer | Vassallo,, Christopher W; Lic. No.: L8418 | 28441 HIGHRIDGE RD 230 ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/6/2022 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/13/2022 | Corrections Issued | ANSON MAGLASANG |
| METHANE-Barrier | 9/13/2022 | Approved | ANSON MAGLASANG |
| METHANE-Subgrade | 9/13/2022 | Approved | ANSON MAGLASANG |
| Footing/Foundation/Slab | 9/19/2022 | Approved | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Corrections Issued | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 11/9/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Deputy Wood Construction | 11/15/2022 | Conditional Approval | ANSON MAGLASANG |
| Interior/Exterior Lathing | 11/23/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/5/2023 | Conditional Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 1/5/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 1/5/2023 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 1/5/2023 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 1/5/2023 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 1/5/2023 | Approved | EUGENE CASSIDY |
| Insulation | 1/24/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 1/24/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 1/30/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 2/27/2023 | Partial Approval | ANSON MAGLASANG |
| Interior/Exterior Lathing | 3/7/2023 | Partial Approval | ANSON MAGLASANG |
| Gas Test | 4/11/2023 | Approved | JOHN KLARIN |
| Special/Order Compliance | 1/8/2025 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Final | 1/13/2025 | Approved | JOSEPH MCGARRY |