9415 W OAKMORE ROAD 90035

Certificate Information: 9415 W OAKMORE ROAD 90035

Application / Permit
21014-30000-04326
Plan Check / Job No.
B21WL03779
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground floor and 2nd floor addition to (E)xisiting 2-story SFD
Permit Issued
Issued on 3/21/2022
Issuing Office
Current Status
CofO Issued on 5/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 FELIPE HERNANDEZ
Corrections Issued 9/28/2021 FELIPE HERNANDEZ
Quality Review Completed 10/4/2021 TARIK SAOUD
Applicant returned to address corrections 1/5/2022 FELIPE HERNANDEZ
Applicant returned to address corrections 1/24/2022 FELIPE HERNANDEZ
Applicant returned to address corrections 2/4/2022 FELIPE HERNANDEZ
Plan Check Approved 3/21/2022 FELIPE HERNANDEZ
Plan Check Approved 3/21/2022 FELIPE HERNANDEZ
Issued 3/21/2022 APPLICANT
Building Plans Picked Up 3/21/2022 APPLICANT
CofO in Progress 5/11/2023 CLAYTON GRAHAM
Permit Finaled 5/20/2023 DANIEL ORRANTE
CofO Issued 5/20/2023 DANIEL ORRANTE
Permit Finaled 5/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/4/2022 FELIPE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 3/18/2022 TAO YANG
Roof/Waste drainage to street Cleared 3/18/2022 TAO YANG
Sewer availability Cleared 3/18/2022 TAO YANG

Contact Information

Architect Palmer,, Mark Jerrold; Lic. No.: C5480 1211 HI POINT STREET      LOS ANGELES, CA 90035
Contractor Owner-Builder       ,
Engineer Mezey,, Steven William; Lic. No.: S2665 14017 HARTSOOK ST      SHERMAN OAKS, CA 91423

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/24/2022 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 3/28/2022 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 4/1/2022 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 4/1/2022 Conditional Approval EVAN COOPER
METHANE-Barrier 4/1/2022 Approved EVAN COOPER
METHANE-Subgrade 4/1/2022 Approved EVAN COOPER
Deputy Reinf. Concrete 4/8/2022 No Result Entered RONALD WEBER
BUILDING-Rough-Frame 5/2/2022 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 5/2/2022 Corrections Issued EVAN COOPER
METHANE-Rough 5/2/2022 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 5/2/2022 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 5/26/2022 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 5/31/2022 Approved EVAN COOPER
PLUMBING-Rough 5/31/2022 Partial Approval EVAN COOPER
Deputy Drilled-In Anchors 6/30/2022 No Result Entered RONALD WEBER
Deputy Wood Construction 7/11/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Not Ready for Inspection EVAN COOPER
Rough-Elec/Plmb/HVAC 8/4/2022 Not Ready for Inspection EVAN COOPER
Deputy Wood Construction 8/10/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/10/2022 Approved OGANES TARAKHCHYAN
METHANE-Rough 8/10/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/12/2022 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/12/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 8/12/2022 Approved OGANES TARAKHCHYAN
HVAC-Rough 8/24/2022 Corrections Issued OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/24/2022 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/25/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 8/25/2022 Approved OGANES TARAKHCHYAN
HVAC-Rough 8/25/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/25/2022 Partial Approval OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 8/25/2022 Approved OGANES TARAKHCHYAN
Wood Frame 8/25/2022 Approved OGANES TARAKHCHYAN
Insulation 8/31/2022 Approved EVAN COOPER
Shower Pan 8/31/2022 Approved EVAN COOPER
Drywall Nailing 9/7/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/7/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 3/10/2023 Approved ASHLEY THOMPSON
Final 3/10/2023 Corrections Issued ASHLEY THOMPSON
Green Building Final 3/10/2023 Corrections Issued ASHLEY THOMPSON
HVAC-Final 3/10/2023 Corrections Issued ASHLEY THOMPSON
PLUMBING-Final 3/10/2023 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Not Ready ASHLEY THOMPSON
Smoke Detectors 3/10/2023 Approved ASHLEY THOMPSON
Final 4/25/2023 Corrections Issued JEREMY TODD
Green Building Final 4/25/2023 Not Ready for Inspection JEREMY TODD
SGSOV-Seismic Gas S/O Valve 4/25/2023 SGSOV Approved JEREMY TODD
Final 5/10/2023 OK to Issue CofO CLAYTON GRAHAM
Green Building Final 5/10/2023 Approved CLAYTON GRAHAM
HVAC-Final 5/10/2023 Approved CLAYTON GRAHAM