19607 W HAMLIN ST 91335
Certificate Information: 19607 W HAMLIN ST 91335
- Application / Permit
- 21014-30000-04294
- Plan Check / Job No.
- B21WL03764
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- addition & conversion of (e) attached garage to ADU per ordinance
- Permit Issued
- Issued on 2/7/2022
- Issuing Office
- Current Status
- CofO Issued on 7/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | KAVIAN REFAHI |
| Corrections Issued | 8/28/2021 | KAVIAN REFAHI |
| Plan Check Approved | 11/3/2021 | KHUONG TRUONG |
| Issued | 2/7/2022 | APPLICANT |
| CofO in Progress | 7/27/2022 | STEVEN BACK |
| CofO Issued | 7/29/2022 | JOHN JANSON |
| Permit Finaled | 7/29/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2021 | JOHN LIN |
| ZI | Cleared | 9/10/2021 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2021 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 10/1/2021 | JOHN LIN |
| Sewer availability | Cleared | 10/1/2021 | JOHN LIN |
| Hydrant and Access approval | Cleared | 10/20/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mah,, Edwin Poy-Dor; Lic. No.: C27141 | 1740 APPIAN WAY MONTEBELLO, CA 90640 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/15/2022 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 3/22/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2022 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 4/26/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 4/26/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 5/2/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 5/6/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 5/6/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2022 | Approved | STEVEN BACK |
| Green Building Rough | 5/11/2022 | Approved | STEVEN BACK |
| Shower Pan | 5/11/2022 | Approved | STEVEN BACK |
| Insulation | 5/13/2022 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 5/23/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 6/6/2022 | Approved | STEVEN BACK |
| Sewer | 6/6/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 7/13/2022 | No Access for Inspection | STEVEN BACK |
| HVAC-Final | 7/13/2022 | No Access for Inspection | STEVEN BACK |
| PLUMBING-Final | 7/13/2022 | No Access for Inspection | STEVEN BACK |
| ELECTRICAL-Final | 7/14/2022 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Final | 7/14/2022 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Final | 7/14/2022 | Approved | STEVEN BACK |
| Final | 7/27/2022 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 7/27/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 7/27/2022 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 7/27/2022 | Approved | STEVEN BACK |
| Smoke Detectors | 7/27/2022 | Approved | STEVEN BACK |