12716 W RUBENS AVE 90066
Certificate Information: 12716 W RUBENS AVE 90066
- Application / Permit
- 21014-30000-04293
- Plan Check / Job No.
- B21WL03763
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel (E) Single family dwelling.
- Permit Issued
- Issued on 6/14/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | ALFREDO JARA |
| Corrections Issued | 9/14/2021 | ALFREDO JARA |
| Quality Review Completed | 9/23/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 11/15/2022 | ALFREDO JARA |
| Plan Check Approved | 2/6/2023 | ALFREDO JARA |
| Building Plans Picked Up | 6/30/2023 | APPLICANT |
| No Progress | 6/12/2024 | ALFREDO JARA |
| Plan Check Approved | 6/12/2024 | ALFREDO JARA |
| Issued | 6/14/2024 | APPLICANT |
| CofO in Progress | 12/31/2024 | MICHAEL ALLEN |
| Permit Finaled | 1/2/2025 | RICHARD STEINBACH |
| CofO Issued | 1/2/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/2/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZI | Cleared | 10/20/2021 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2021 | DINAH GARIN |
| Sewer availability | Cleared | 10/21/2021 | DINAH GARIN |
| Construction near power lines | Cleared | 1/14/2022 | RIDWAN HARDY |
| Specific Plan | Cleared | 2/1/2022 | PEDRO AYALA |
| Roof/Waste drainage to street | Cleared | 1/23/2023 | CINDY QI |
Contact Information
| Contractor | Ayon Construction; Lic. No.: 1044491-B | 2225 HOLLY AVE ARCADIA, CA 91007 |
| Engineer | Attaalla,, Sayed Ahmed; Lic. No.: S5339 | 11254 HANNUM AVE CULVER CITY, CA 90230 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/18/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/26/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Shower Pan | 7/8/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/24/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Approved | TEMISTOCLES CAAL |
| Gas Test | 7/24/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 7/24/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Rough | 7/24/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 7/24/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 7/29/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 7/29/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 7/29/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 8/1/2024 | Conditional Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 8/1/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 8/1/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/1/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 8/7/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/7/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 8/13/2024 | Approved | TEMISTOCLES CAAL |
| Final | 11/12/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| Green Building Final | 11/12/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 11/12/2024 | SGSOV Not Ready | MICHAEL ALLEN |
| Smoke Detectors | 11/12/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Final | 11/18/2024 | Approved | MICHAEL ALLEN |
| Final | 11/18/2024 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 11/18/2024 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 11/18/2024 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Final | 11/18/2024 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2024 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 11/18/2024 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 12/30/2024 | Approved | MICHAEL ALLEN |
| Final | 12/30/2024 | OK to Issue CofO | MICHAEL ALLEN |
| Green Building Final | 12/30/2024 | Approved | MICHAEL ALLEN |
| HVAC-Final | 12/30/2024 | Approved | MICHAEL ALLEN |