9450 W SIERRA MAR DR 90069

Certificate Information: 9450 W SIERRA MAR DR 90069

Application / Permit
21014-30000-04292
Plan Check / Job No.
B21WL03762
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel of an (e) S.F.D. w/ attached garage. New addition above the garage. *** 1 of 2 ***
Permit Issued
Issued on 7/18/2022
Issuing Office
Current Status
Issued on 7/18/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/24/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 RICHARD GARCIA
Corrections Issued 9/12/2021 RICHARD GARCIA
Quality Review Completed 9/23/2021 TARIK SAOUD
Applicant returned to address corrections 2/22/2022 RICHARD GARCIA
Applicant returned to address corrections 3/3/2022 RICHARD GARCIA
Building Plans Picked Up 3/7/2022 APPLICANT
Plan Check Approved 5/26/2022 RICHARD GARCIA
Issued 7/18/2022 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 11/29/2021 RUBEN VASQUEZ
Roof/Waste drainage to street Cleared 12/20/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 1/3/2022 STEVE MELGAR
Sewer availability Cleared 1/3/2022 STEVE MELGAR
Grading Pre-Inspection Cleared 3/3/2022 RICHARD GARCIA
BHO/Hillside ordinance Cleared 3/31/2022 TRACY TATE
BHO/Hillside ordinance Cleared 3/31/2022 TRACY TATE
BHO/Hillside ordinance Cleared 3/31/2022 TRACY TATE
BHO/Hillside ordinance Cleared 3/31/2022 TRACY TATE
BHO/Hillside ordinance Cleared 3/31/2022 TRACY TATE

Contact Information

Contractor Noesis Builders Inc; Lic. No.: 1046562-B 8383 WILSHIRE BOULEVARD SUITE   740    BEVERLY HILLS, CA 90211
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 9/29/2022 Corrections Issued RAUL BARAJAS
Pre-Inspection 10/6/2022 Partial Inspection RAUL BARAJAS
Special/Order Compliance 11/30/2022 Approved RUBEN SALAS
Pre-Inspection 12/7/2022 Not Ready for Inspection RAUL BARAJAS
Piling/Pier/Caisson 12/29/2022 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 1/26/2023 Corrections Issued RAUL BARAJAS
Deputy Reinf. Concrete 3/14/2023 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/12/2023 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/27/2023 Approved RAUL BARAJAS
Special/Order Compliance 4/27/2023 Corrections Issued RAUL BARAJAS
Deputy Steel/Welding 6/22/2023 Conditional Approval RAUL BARAJAS
PLUMBING-Rough 8/8/2023 Partial Approval RAUL BARAJAS
HVAC-Rough 8/22/2023 Partial Approval RAUL BARAJAS
Deputy Wood Construction 9/21/2023 Conditional Approval RAUL BARAJAS
ELECTRICAL-Rough 9/21/2023 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Corrections Issued RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 5/1/2024 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 5/3/2024 Partial Approval RAUL BARAJAS
Service/Power Release 5/3/2024 Corrections Issued RAUL BARAJAS
Shower Pan 7/8/2025 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 7/11/2025 No Access for Inspection JOSH MEISTER
ELECTRICAL-Rough 7/11/2025 No Access for Inspection JOSH MEISTER
Green Building Rough 7/11/2025 No Access for Inspection JOSH MEISTER
HVAC-Rough 7/11/2025 No Access for Inspection JOSH MEISTER
PLUMBING-Rough 7/11/2025 No Access for Inspection JOSH MEISTER
Wood Frame 7/11/2025 No Access for Inspection JOSH MEISTER
Pre-Inspection 7/15/2025 No Access for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 7/18/2025 Corrections Issued RAUL BARAJAS
HVAC-Rough 7/18/2025 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 7/18/2025 Corrections Issued RAUL BARAJAS
Rough-Elec/Plmb/HVAC 8/12/2025 Approved BRENDAN MORELLI
Interior/Exterior Lathing 10/3/2025 Partial Approval ALEX COLIN
Interior/Exterior Lathing 11/14/2025 Approved BRENDAN MORELLI
Pre-Inspection 11/14/2025 Partial Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 12/1/2025 Partial Approval CRAIG VAUGHAN
Green Building Rough 12/1/2025 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 12/1/2025 Approved CRAIG VAUGHAN
Wood Frame 12/1/2025 Corrections Issued CRAIG VAUGHAN
Insulation 12/15/2025 Approved DAVID WILLIAMS
Drywall Nailing 1/27/2026 Approved DAVID WILLIAMS