2046 N HOBART BLVD 90027
Certificate Information: 2046 N HOBART BLVD 90027
- Application / Permit
- 21014-30000-04218
- Plan Check / Job No.
- B21WL03697
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and Addition to (E) 2-Story S.F.D w/Attached Garage
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | DAVID CASTILLO |
| Corrections Issued | 10/7/2021 | DAVID CASTILLO |
| Quality Review Completed | 10/18/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 1/27/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 1/31/2022 | APPLICANT |
| Plan Check Approved | 8/29/2022 | ARTIN ZARUKIAN |
| Issued | 8/29/2022 | APPLICANT |
| CofO in Progress | 9/21/2023 | JOAQUIN GREENOUGH |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
| CofO Issued | 9/21/2023 | DEROLD HAUFF |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/10/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 11/10/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 11/10/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 11/10/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 11/10/2021 | WALLIE JONG |
| Highway dedication | Cleared | 11/10/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 12/10/2021 | SERGIO VALENZUELA |
| Permit | Cleared | 12/14/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 12/14/2021 | WALLIE JONG |
| Sewer availability | Cleared | 12/14/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2021 | WALLIE JONG |
| Trees in Parkway | Cleared | 1/27/2022 | ADALBERTO VERA |
| City Hist. Cultural Monument | Cleared | 2/3/2022 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 2/3/2022 | LAMBERT GIESSINGER |
Contact Information
| Contractor | Lusk House Llc; Lic. No.: 1093899-B | 15543 ROYAL RIDGE ROAD SHERMAN OAKS, CA 91403 |
| Engineer | Galbreath,, Sean Martin; Lic. No.: S5653 | 600 SOUTH LAKE AVE STE 308 PASADENA, CA 91106 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 11/17/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 11/29/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Piling/Pier/Caisson | 11/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/5/2022 | Approved | JOAQUIN GREENOUGH |
| Piling/Pier/Caisson | 12/5/2022 | Approved | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 12/9/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/9/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/9/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Piling/Pier/Caisson | 12/9/2022 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 12/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Reinforced Concrete Frame | 12/13/2022 | Approved | JOAQUIN GREENOUGH |
| Structural Steel Frame | 12/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 12/13/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Insulation | 12/14/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 12/22/2022 | Conditional Approval | RUBEN SALAS |
| Deputy Wood Construction | 12/22/2022 | Conditional Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2023 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 2/2/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 2/2/2023 | Approved | JOAQUIN GREENOUGH |
| Special/Order Compliance | 2/2/2023 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 2/14/2023 | Partial Approval | RAUL BARAJAS |
| Insulation | 2/23/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 2/23/2023 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/6/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 3/6/2023 | Approved | STUART CHAPMAN |
| Insulation | 3/6/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 3/10/2023 | Approved | STUART CHAPMAN |
| Final | 9/12/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/12/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 9/12/2023 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 9/12/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 9/18/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 9/18/2023 | Approved | JOAQUIN GREENOUGH |