7520 S KENTWOOD AVE 90045
Certificate Information: 7520 S KENTWOOD AVE 90045
- Application / Permit
- 21014-30000-04200
- Plan Check / Job No.
- B21WL03682
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to an (E) Single family dwelling.
- Permit Issued
- Issued on 8/5/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | ALFREDO JARA |
| Corrections Issued | 8/24/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 3/16/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 3/30/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 4/14/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 4/21/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 4/25/2022 | APPLICANT |
| Plan Check Approved | 4/29/2022 | KHUONG TRUONG |
| Issued | 8/5/2022 | APPLICANT |
| CofO in Progress | 5/26/2023 | HERBERT GIRON |
| Permit Finaled | 6/5/2023 | DANIEL ORRANTE |
| CofO Issued | 6/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/22/2021 | PETE EYRE |
| Low Impact Development | Cleared | 3/2/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/4/2022 | JOSE RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2022 | JOSE RODRIGUEZ |
| Sewer availability | Cleared | 3/18/2022 | JOSE RODRIGUEZ |
| GPI Written Notices | Cleared | 3/20/2022 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 3/20/2022 | ALFREDO JARA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Regal Construction & Remodeling Inc; Lic. No.: 909023-B | 19537 1/2 VENTURA BLVD TARZANA, CA 91356 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/9/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 9/9/2022 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/4/2022 | Conditional Approval | HERBERT GIRON |
| Green Building Rough | 10/4/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 10/4/2022 | Partial Approval | HERBERT GIRON |
| Wood Frame | 10/4/2022 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 10/7/2022 | Approved | HERBERT GIRON |
| Insulation | 10/7/2022 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Partial Approval | HERBERT GIRON |
| Deputy Wood Construction | 10/20/2022 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 10/21/2022 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 10/21/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Approved | HERBERT GIRON |
| HVAC-Rough | 11/3/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/18/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 11/18/2022 | Approved | HERBERT GIRON |
| HVAC-Rough | 11/18/2022 | Conditional Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 11/18/2022 | Partial Approval | HERBERT GIRON |
| Insulation | 11/23/2022 | Approved | HERBERT GIRON |
| Special/Order Compliance | 11/23/2022 | Corrections Issued | HERBERT GIRON |
| Shower Pan | 11/28/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 12/2/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 12/2/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 4/19/2023 | Corrections Issued | HERBERT GIRON |
| Final | 4/19/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 4/19/2023 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 4/19/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 4/19/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 4/19/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 5/3/2023 | Approved | HERBERT GIRON |
| Final | 5/3/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 5/3/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 5/3/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 5/3/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 5/3/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 5/3/2023 | Approved | HERBERT GIRON |
| Final | 5/26/2023 | OK to Issue CofO | HERBERT GIRON |