2968 N SUNNYNOOK DR 90039

Certificate Information: 2968 N SUNNYNOOK DR 90039

Application / Permit
21014-30000-04185
Plan Check / Job No.
B21WL03664
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel & addition to the rear of an existing 1-story S.F.D. All work per engineer's design and details
Permit Issued
Issued on 10/8/2021
Issuing Office
Current Status
CofO Issued on 10/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 RICHARD GARCIA
Corrections Issued 8/21/2021 RICHARD GARCIA
Building Plans Picked Up 8/26/2021 APPLICANT
Applicant returned to address corrections 9/16/2021 JASON JANGADA
Plan Check Approved 9/30/2021 RICHARD GARCIA
Issued 10/8/2021 APPLICANT
CofO in Progress 10/4/2022 HAMIK HARTOUNIAN
Permit Finaled 10/6/2022 DEROLD HAUFF
CofO Issued 10/6/2022 DEROLD HAUFF
Permit Finaled 10/6/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/3/2021 RENZ SORIANO
Sewer availability Cleared 9/3/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/7/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/27/2022 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/1/2022 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/4/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/12/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 5/12/2022 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 5/12/2022 Approved HAMIK HARTOUNIAN
Wood Frame 5/12/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/27/2022 Approved CRAIG VAUGHAN
Green Building Rough 5/27/2022 Approved CRAIG VAUGHAN
HVAC-Rough 5/27/2022 Partial Approval CRAIG VAUGHAN
MERV13>=Rough 5/27/2022 Approved CRAIG VAUGHAN
HVAC-Rough 6/7/2022 Approved HAMIK HARTOUNIAN
Insulation 6/7/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/7/2022 Partial Approval HAMIK HARTOUNIAN
Insulation 6/10/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 6/14/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/14/2022 Partial Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/27/2022 Approved HAMIK HARTOUNIAN
Shower Pan 6/27/2022 Conditional Approval HAMIK HARTOUNIAN
Final 9/8/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/8/2022 Approved HAMIK HARTOUNIAN
Green Building Final 9/8/2022 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Final 9/8/2022 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/8/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 9/8/2022 Approved HAMIK HARTOUNIAN
Final 9/21/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 9/21/2022 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Final 9/21/2022 Partial Inspection HAMIK HARTOUNIAN
Final 9/23/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 9/23/2022 Approved HAMIK HARTOUNIAN
MERV13>=Final 9/23/2022 Approved HAMIK HARTOUNIAN
Gas Test 9/27/2022 Approved HAMIK HARTOUNIAN
Final 9/29/2022 OK to Issue CofO HAMIK HARTOUNIAN