939 S KENISTON AVE 90019

Certificate Information: 939 S KENISTON AVE 90019

Application / Permit
21014-30000-04010
Plan Check / Job No.
B21WL03567
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and Remodel to (E) 1-Story S.F.D per WFPP ** 1 of 2 **
Permit Issued
Issued on 1/20/2022
Issuing Office
Current Status
CofO Issued on 9/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 DAVID CASTILLO
Corrections Issued 8/30/2021 DAVID CASTILLO
Quality Review Completed 9/7/2021 TARIK SAOUD
Applicant returned to address corrections 10/19/2021 DAVID CASTILLO
Applicant returned to address corrections 11/4/2021 DAVID CASTILLO
Applicant returned to address corrections 11/8/2021 DAVID CASTILLO
Applicant returned to address corrections 11/18/2021 DAVID CASTILLO
Applicant returned to address corrections 12/1/2021 DAVID CASTILLO
Applicant returned to address corrections 12/10/2021 DAVID CASTILLO
Plan Check Approved 1/14/2022 DAVID CASTILLO
Issued 1/20/2022 APPLICANT
Building Plans Picked Up 1/24/2022 APPLICANT
CofO in Progress 9/19/2022 MICHAEL LEWIS
Permit Finaled 9/19/2022 RONALD MYRICK
CofO Issued 9/19/2022 RONALD MYRICK
Permit Finaled 9/19/2022 RONALD MYRICK

Permit Application Clearance Information

Sewer availability Cleared 10/20/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/21/2021 STEVE MELGAR
Low Impact Development Cleared 12/15/2021 SAHIL SHARMA
Roof/Waste drainage to street Cleared 12/23/2021 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/8/2022 Approved ARTHUR SARGSYAN
METHANE-Barrier 2/8/2022 Approved ARTHUR SARGSYAN
METHANE-Subgrade 2/8/2022 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Partial Approval ARTHUR SARGSYAN
Service/Power Release 3/11/2022 Approved ARTHUR SARGSYAN
Underground Mechanical 3/22/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 4/29/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 4/29/2022 Approved ARTHUR SARGSYAN
Gas Test 4/29/2022 Approved ARTHUR SARGSYAN
Green Building Rough 4/29/2022 Approved ARTHUR SARGSYAN
HVAC-Rough 4/29/2022 Approved ARTHUR SARGSYAN
PLUMBING-Rough 4/29/2022 Approved ARTHUR SARGSYAN
Drywall Nailing 5/6/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 5/13/2022 Partial Inspection ARTHUR SARGSYAN
ELECTRICAL-Final 8/18/2022 Corrections Issued ALIZAH MAYAGOITIA
Final 8/18/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 8/18/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 8/18/2022 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 8/18/2022 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/18/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 8/18/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 8/22/2022 Approved STUART CHAPMAN
Final 8/22/2022 Corrections Issued STUART CHAPMAN
HVAC-Final 8/22/2022 Approved STUART CHAPMAN
PLUMBING-Final 8/22/2022 Approved STUART CHAPMAN
Final 9/7/2022 Corrections Issued MICHAEL LEWIS
Green Building Final 9/7/2022 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved MICHAEL LEWIS
Final 9/19/2022 OK to Issue CofO MICHAEL LEWIS