2749 S TILDEN AVE 90064

Certificate Information: 2749 S TILDEN AVE 90064

Application / Permit
21014-30000-04008
Plan Check / Job No.
B21WL03564
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1ST AND 2ND FLOOR ADDITION (1499 SQFT) TO EXISTING 1-STORY SINGLE FAMILY DWELLING W/ATTACHED FRONT OPEN TRELLIS.W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/20/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 TROY DEGUZMAN
Corrections Issued 8/31/2021 TROY DEGUZMAN
Quality Review Completed 9/2/2021 OMID HEDAYAT
Building Plans Picked Up 9/3/2021 APPLICANT
Applicant returned to address corrections 10/15/2021 TROY DEGUZMAN
Applicant returned to address corrections 12/13/2021 TROY DEGUZMAN
Plan Check Approved 5/13/2024 PETER MOSESIAN
Issued 6/20/2024 APPLICANT
CofO in Progress 7/14/2025 DAVID FEILER
Permit Finaled 7/17/2025 RICHARD STEINBACH
CofO Issued 7/17/2025 RICHARD STEINBACH
Permit Finaled 7/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/25/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 10/25/2021 SAUL GARCIA
Sewer availability Cleared 10/25/2021 SAUL GARCIA
Specific Plan Cleared 10/25/2021 KENTON TRINH
Green Code Cleared 10/27/2021 TROY DEGUZMAN
Grading Pre-Inspection Cleared 11/30/2021 BRIAN MILLER
Miscellaneous Cleared 12/6/2021 KENTON TRINH
GPI Written Notices Cleared 12/16/2021 BRIAN MILLER
Hydrant and Access approval Cleared 1/29/2022 GILBERT URREA
Roof/Waste drainage to street Cleared 4/4/2022 JOSE HERNANDEZ
Low Impact Development Cleared 4/7/2022 TROY DEGUZMAN

Contact Information

Architect Youssefzadeh,, Atabak; Lic. No.: C22727 1401 WESTWOOD BLVD #320      LOS ANGELES, CA 90024
Contractor Owner-Builder       ,
Engineer Mangoli,, Arash; Lic. No.: C84319 1727 BENTLEY AVE APT 211      LOS ANGELES, CA 90025

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/26/2024 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 8/27/2024 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 8/27/2024 Corrections Issued MICHAEL PELHAM
Special/Order Compliance 8/27/2024 Partial Inspection DANIEL VERA
Special/Order Compliance 8/27/2024 Partial Inspection MICHAEL ALLEN
Special/Order Compliance 8/27/2024 Partial Inspection REGINA MENDEZ
Footing/Foundation/Slab 9/11/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 10/17/2024 Partial Approval KIRK SANDERS
Underground Mechanical 10/22/2024 Approved DANIEL VERA
Excavation/Setback/Form/Re-Bar 10/25/2024 Approved DANIEL VERA
Footing/Foundation/Slab 10/25/2024 Approved DANIEL VERA
Sewer 11/6/2024 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 11/20/2024 Corrections Issued DANIEL VERA
Deputy Wood Construction 11/21/2024 Conditional Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Approved DANIEL VERA
Underground Mechanical 11/22/2024 Partial Approval DANIEL VERA
Deputy Wood Construction 12/4/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Corrections Issued DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Approved DANIEL VERA
HVAC-Rough 12/12/2024 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Not Ready for Inspection DANIEL VERA
HVAC-Rough 12/23/2024 Not Ready for Inspection DANIEL VERA
Deputy Wood Construction 12/24/2024 Conditional Approval MICHAEL PELHAM
HVAC-Rough 12/31/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 1/10/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/10/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 1/10/2025 Approved JESUS RODRIGUEZ
Underground Mechanical 1/10/2025 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 1/29/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 1/31/2025 Approved EVAN COOPER
Green Building Rough 1/31/2025 Approved EVAN COOPER
Insulation 1/31/2025 Corrections Issued EVAN COOPER
MERV13>=Rough 1/31/2025 Approved EVAN COOPER
Insulation 2/6/2025 Conditional Approval KIRK SANDERS
Service/Power Release 2/6/2025 Not Ready for Inspection KIRK SANDERS
Drywall Nailing 2/14/2025 Approved DANIEL VERA
Interior/Exterior Lathing 2/20/2025 Partial Approval BOBBY KEY
Interior/Exterior Lathing 2/21/2025 Approved BOBBY KEY
Shower Pan 2/21/2025 Approved KENNETH NAGLE
ELECTRICAL-Final 4/4/2025 Approved WILBER ROSALES
Service/Power Release 4/4/2025 Not Ready for Inspection WILBER ROSALES
HVAC-Final 4/24/2025 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Final 4/24/2025 Not Ready for Inspection ARAM AVEDISIAN
Service/Power Release 4/24/2025 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Final 4/29/2025 Approved ARAM AVEDISIAN
PLUMBING-Final 4/29/2025 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 5/5/2025 Approved BOBBY KEY
Service/Power Release 5/5/2025 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 6/3/2025 Corrections Issued STEPHANIE SWANSON
Final 6/3/2025 Corrections Issued STEPHANIE SWANSON
Green Building Final 6/3/2025 Approved STEPHANIE SWANSON
HVAC-Final 6/3/2025 Corrections Issued STEPHANIE SWANSON
MERV13>=Final 6/3/2025 Approved STEPHANIE SWANSON
PLUMBING-Final 6/3/2025 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 6/3/2025 Approved STEPHANIE SWANSON
Gas Test 6/4/2025 Not Ready for Inspection STEPHANIE SWANSON
Gas Test 6/6/2025 Approved WILBER ROSALES
ELECTRICAL-Final 6/16/2025 Approved WILBER ROSALES
Final 6/16/2025 Corrections Issued WILBER ROSALES
HVAC-Final 6/16/2025 Approved WILBER ROSALES
PLUMBING-Final 6/16/2025 Approved WILBER ROSALES
Service/Power Release 6/16/2025 Not Ready for Inspection WILBER ROSALES
Final 7/14/2025 OK to Issue CofO DAVID FEILER
Service/Power Release 7/14/2025 Approved DAVID FEILER