- Work Description
- NEW 1ST AND 2ND FLOOR ADDITION (1499 SQFT) TO EXISTING 1-STORY SINGLE FAMILY DWELLING W/ATTACHED FRONT OPEN TRELLIS.W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/20/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | TROY DEGUZMAN |
| Corrections Issued | 8/31/2021 | TROY DEGUZMAN |
| Quality Review Completed | 9/2/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/3/2021 | APPLICANT |
| Applicant returned to address corrections | 10/15/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 12/13/2021 | TROY DEGUZMAN |
| Plan Check Approved | 5/13/2024 | PETER MOSESIAN |
| Issued | 6/20/2024 | APPLICANT |
| CofO in Progress | 7/14/2025 | DAVID FEILER |
| Permit Finaled | 7/17/2025 | RICHARD STEINBACH |
| CofO Issued | 7/17/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/17/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/25/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 10/25/2021 | SAUL GARCIA |
| Specific Plan | Cleared | 10/25/2021 | KENTON TRINH |
| Green Code | Cleared | 10/27/2021 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 11/30/2021 | BRIAN MILLER |
| Miscellaneous | Cleared | 12/6/2021 | KENTON TRINH |
| GPI Written Notices | Cleared | 12/16/2021 | BRIAN MILLER |
| Hydrant and Access approval | Cleared | 1/29/2022 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | JOSE HERNANDEZ |
| Low Impact Development | Cleared | 4/7/2022 | TROY DEGUZMAN |
Contact Information
| Architect | Youssefzadeh,, Atabak; Lic. No.: C22727 | 1401 WESTWOOD BLVD #320 LOS ANGELES, CA 90024 |
| Contractor | Owner-Builder | , |
| Engineer | Mangoli,, Arash; Lic. No.: C84319 | 1727 BENTLEY AVE APT 211 LOS ANGELES, CA 90025 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/26/2024 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 8/27/2024 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 8/27/2024 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 8/27/2024 | Partial Inspection | DANIEL VERA |
| Special/Order Compliance | 8/27/2024 | Partial Inspection | MICHAEL ALLEN |
| Special/Order Compliance | 8/27/2024 | Partial Inspection | REGINA MENDEZ |
| Footing/Foundation/Slab | 9/11/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/17/2024 | Partial Approval | KIRK SANDERS |
| Underground Mechanical | 10/22/2024 | Approved | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 10/25/2024 | Approved | DANIEL VERA |
| Footing/Foundation/Slab | 10/25/2024 | Approved | DANIEL VERA |
| Sewer | 11/6/2024 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Corrections Issued | DANIEL VERA |
| Deputy Wood Construction | 11/21/2024 | Conditional Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2024 | Approved | DANIEL VERA |
| Underground Mechanical | 11/22/2024 | Partial Approval | DANIEL VERA |
| Deputy Wood Construction | 12/4/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2024 | Approved | DANIEL VERA |
| HVAC-Rough | 12/12/2024 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 12/23/2024 | Not Ready for Inspection | DANIEL VERA |
| Deputy Wood Construction | 12/24/2024 | Conditional Approval | MICHAEL PELHAM |
| HVAC-Rough | 12/31/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 1/10/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/10/2025 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 1/10/2025 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/29/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 1/31/2025 | Approved | EVAN COOPER |
| Green Building Rough | 1/31/2025 | Approved | EVAN COOPER |
| Insulation | 1/31/2025 | Corrections Issued | EVAN COOPER |
| MERV13>=Rough | 1/31/2025 | Approved | EVAN COOPER |
| Insulation | 2/6/2025 | Conditional Approval | KIRK SANDERS |
| Service/Power Release | 2/6/2025 | Not Ready for Inspection | KIRK SANDERS |
| Drywall Nailing | 2/14/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 2/20/2025 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 2/21/2025 | Approved | BOBBY KEY |
| Shower Pan | 2/21/2025 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 4/4/2025 | Approved | WILBER ROSALES |
| Service/Power Release | 4/4/2025 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Final | 4/24/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 4/24/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Service/Power Release | 4/24/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Final | 4/29/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 4/29/2025 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 5/5/2025 | Approved | BOBBY KEY |
| Service/Power Release | 5/5/2025 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 6/3/2025 | Corrections Issued | STEPHANIE SWANSON |
| Final | 6/3/2025 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 6/3/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 6/3/2025 | Corrections Issued | STEPHANIE SWANSON |
| MERV13>=Final | 6/3/2025 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 6/3/2025 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 6/3/2025 | Approved | STEPHANIE SWANSON |
| Gas Test | 6/4/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Gas Test | 6/6/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 6/16/2025 | Approved | WILBER ROSALES |
| Final | 6/16/2025 | Corrections Issued | WILBER ROSALES |
| HVAC-Final | 6/16/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 6/16/2025 | Approved | WILBER ROSALES |
| Service/Power Release | 6/16/2025 | Not Ready for Inspection | WILBER ROSALES |
| Final | 7/14/2025 | OK to Issue CofO | DAVID FEILER |
| Service/Power Release | 7/14/2025 | Approved | DAVID FEILER |