528-530 S AVONDALE AVE 90049
Certificate Information: 528-530 S AVONDALE AVE 90049
- Application / Permit
- 21014-30000-03877
- Plan Check / Job No.
- B21WL03434
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story ADU addition and major remodel to (e) S.F.D. (leave 1 existing wall to remain)
- Permit Issued
- Issued on 11/8/2021
- Issuing Office
- Current Status
- CofO Issued on 3/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | TARIK SAOUD |
| Corrections Issued | 8/24/2021 | TARIK SAOUD |
| Quality Review Completed | 8/25/2021 | CHIHARU SUZUKI |
| Plan Check Approved | 11/4/2021 | TARIK SAOUD |
| Issued | 11/8/2021 | APPLICANT |
| Building Plans Picked Up | 12/1/2021 | APPLICANT |
| CofO in Progress | 3/6/2023 | CLAYTON GRAHAM |
| Permit Finaled | 3/10/2023 | DANIEL ORRANTE |
| CofO Issued | 3/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/30/2021 | KEVIN ARUCAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | DINAH GARIN |
| Sewer availability | Cleared | 8/31/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 10/11/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/20/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 10/27/2021 | DINAH GARIN |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Pillar Building Group Llc; Lic. No.: 1017041-B | 8109 ORION AVE VAN NUYS, CA 91406 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/31/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 1/31/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 2/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Grounding or Bonding | 2/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 2/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 2/9/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 2/14/2022 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Partial Approval | KENNETH NAGLE |
| Special/Order Compliance | 5/19/2022 | Corrections Issued | KENNETH NAGLE |
| BUILDING-Rough-Frame | 6/22/2022 | Partial Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/22/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/1/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/1/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/18/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/18/2022 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/21/2022 | Approved | JOHN KIDWELL |
| Green Building Rough | 7/21/2022 | Approved | JOHN KIDWELL |
| Insulation | 8/3/2022 | Approved | PATRICK QUALEY |
| Underground Mechanical | 11/21/2022 | Partial Approval | ASHLEY THOMPSON |
| Underground Mechanical | 12/22/2022 | Corrections Issued | ASHLEY THOMPSON |
| Service/Power Release | 1/6/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Final | 1/10/2023 | Corrections Issued | ASHLEY THOMPSON |
| Service/Power Release | 1/10/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Final | 1/13/2023 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 1/13/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Underground Mechanical | 1/13/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Underground Mechanical | 1/20/2023 | Partial Approval | CLAYTON GRAHAM |
| Service/Power Release | 1/23/2023 | Approved | DAVID FEILER |
| HVAC-Final | 1/26/2023 | Partial Inspection | JULIAN AMAYA |
| PLUMBING-Rough | 1/26/2023 | Partial Inspection | JULIAN AMAYA |
| Gas Test | 2/2/2023 | Approved | DAVID FEILER |
| PLUMBING-Final | 2/2/2023 | Partial Approval | DAVID FEILER |
| HVAC-Final | 2/3/2023 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 2/8/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Final | 2/8/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Final | 2/10/2023 | Approved | CLAYTON GRAHAM |
| Final | 2/24/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 2/24/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 2/24/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Smoke Detectors | 2/24/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 3/3/2023 | OK to Issue CofO | CLAYTON GRAHAM |
| Green Building Final | 3/3/2023 | Approved | CLAYTON GRAHAM |
| Smoke Detectors | 3/3/2023 | Approved | CLAYTON GRAHAM |