909 W ADAMS BLVD 90007

Certificate Information: 909 W ADAMS BLVD 90007

Application / Permit
21014-30000-03848
Plan Check / Job No.
B21WL03402
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(16) Library non-profit
Work Description
ADDITION OF ELEVATOR AND HALLWAY TO EXISTING 2-STORY TYPE VB NON-PROFIT LIBRARY, REVISION TO EXISTING HVAC, AND RESTRIPING EXISTING PARKING LOT.
Permit Issued
Issued on 8/11/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 SERGIO SILVA
Disabled Access Plans Picked Up 9/2/2021 APPLICANT
Corrections Issued 9/8/2021 SERGIO SILVA
Quality Review Completed 9/20/2021 TARIK SAOUD
Applicant returned to address corrections 3/9/2022 SERGIO SILVA
Building Plans Picked Up 3/30/2022 APPLICANT
Green Plans Picked Up 4/15/2022 APPLICANT
Applicant returned to address corrections 5/2/2022 SERGIO SILVA
Plan Check Approved 5/12/2022 SERGIO SILVA
Issued 8/11/2022 APPLICANT
CofO in Progress 11/16/2023 MARTIN TAVITIAN
CofO Issued 2/9/2024 ERNESTO CORRAL
Permit Finaled 2/9/2024 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 2/1/2022 RUBEN VASQUEZ
CPC Cleared 2/1/2022 RUBEN VASQUEZ
Miscellaneous Cleared 2/1/2022 RUBEN VASQUEZ
Miscellaneous Cleared 2/1/2022 RUBEN VASQUEZ
Miscellaneous Cleared 2/1/2022 RUBEN VASQUEZ
Miscellaneous Cleared 2/1/2022 RUBEN VASQUEZ
ZI Cleared 2/1/2022 RUBEN VASQUEZ
Prkng lot landscape/Water mgmt Cleared 2/2/2022 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 2/18/2022 CELINA MORENO
Permit Cleared 2/18/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 2/18/2022 CELINA MORENO
Sewer availability Cleared 2/18/2022 CELINA MORENO
City Hist. Cultural Monument Cleared 3/8/2022 KATIE DEBIASE
HPOZ Cleared 3/8/2022 KATIE DEBIASE
Historic monument Cleared 3/8/2022 KATIE DEBIASE
ZI Cleared 3/8/2022 KATIE DEBIASE
Green Code Cleared 4/14/2022 RICHARD GARCIA
DAS Clearance Cleared 4/21/2022 SERGIO SILVA

Contact Information

Architect Kaplan,, David Alan; Lic. No.: C12875 2419 PIER AVE.      SANTA MONICA, CA 90405
Contractor Austin Commercial L P; Lic. No.: 806038-B 3535 TRAVIS ST SUITE 300      DALLAS, TX 75204
Engineer Youssef,, Nabih Fouad Guirg; Lic. No.: S2026 550 S HOPE ST STE 1700      LOS ANGELES, CA 90071

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 12/8/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 12/9/2022 Partial Inspection ALAN MORELOS
Green Building Rough 12/9/2022 Not Ready for Inspection ALAN MORELOS
METHANE-Barrier 12/9/2022 Approved ALAN MORELOS
METHANE-Rough 12/9/2022 Approved ALAN MORELOS
METHANE-Subgrade 12/9/2022 Approved ALAN MORELOS
Wood Frame 12/9/2022 Partial Inspection ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 No Access for Inspection ALAN MORELOS
Green Building Rough 12/13/2022 Not Ready for Inspection ALAN MORELOS
Wood Frame 12/13/2022 No Access for Inspection ALAN MORELOS
Excavation/Setback/Form/Re-Bar 12/14/2022 Not Ready for Inspection RAMAZANALI ALMASI
Footing/Foundation/Slab 12/14/2022 Not Ready for Inspection RAMAZANALI ALMASI
Deputy Drilled-In Anchors 12/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/16/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Partial Approval ALAN MORELOS
Excavation/Setback/Form/Re-Bar 12/22/2022 Partial Approval ALAN MORELOS
Footing/Foundation/Slab 12/22/2022 Partial Approval ALAN MORELOS
Pre-Inspection 12/22/2022 Partial Approval MARTIN TAVITIAN
Footing/Foundation/Slab 1/25/2023 Approved MARTIN TAVITIAN
Deputy Drilled-In Anchors 2/22/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Other (see comments) 2/22/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 2/23/2023 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 2/23/2023 Approved MARTIN TAVITIAN
Deputy Steel/Welding 3/7/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 4/3/2023 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 4/3/2023 Partial Approval MARTIN TAVITIAN
Insulation 4/27/2023 Partial Approval MARTIN TAVITIAN
Final 8/9/2023 Not Ready for Inspection ALAN MORELOS
Green Building Final 8/9/2023 Not Ready for Inspection ALAN MORELOS
Green Building Rough 8/9/2023 Approved ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 8/9/2023 SGSOV Not Required ALAN MORELOS
Smoke Detectors 8/9/2023 Not Ready for Inspection ALAN MORELOS
Structural Steel Frame 8/9/2023 Approved ALAN MORELOS
Wood Frame 8/9/2023 Approved ALAN MORELOS
Final 11/7/2023 Conditional Approval MARTIN TAVITIAN
Green Building Final 11/7/2023 Approved MARTIN TAVITIAN
Smoke Detectors 11/7/2023 Approved MARTIN TAVITIAN