909 W ADAMS BLVD 90007
Certificate Information: 909 W ADAMS BLVD 90007
- Application / Permit
- 21014-30000-03848
- Plan Check / Job No.
- B21WL03402
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Library non-profit
- Work Description
- ADDITION OF ELEVATOR AND HALLWAY TO EXISTING 2-STORY TYPE VB NON-PROFIT LIBRARY, REVISION TO EXISTING HVAC, AND RESTRIPING EXISTING PARKING LOT.
- Permit Issued
- Issued on 8/11/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | SERGIO SILVA |
| Disabled Access Plans Picked Up | 9/2/2021 | APPLICANT |
| Corrections Issued | 9/8/2021 | SERGIO SILVA |
| Quality Review Completed | 9/20/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 3/9/2022 | SERGIO SILVA |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Green Plans Picked Up | 4/15/2022 | APPLICANT |
| Applicant returned to address corrections | 5/2/2022 | SERGIO SILVA |
| Plan Check Approved | 5/12/2022 | SERGIO SILVA |
| Issued | 8/11/2022 | APPLICANT |
| CofO in Progress | 11/16/2023 | MARTIN TAVITIAN |
| CofO Issued | 2/9/2024 | ERNESTO CORRAL |
| Permit Finaled | 2/9/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/1/2022 | RUBEN VASQUEZ |
| CPC | Cleared | 2/1/2022 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/1/2022 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/1/2022 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/1/2022 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/1/2022 | RUBEN VASQUEZ |
| ZI | Cleared | 2/1/2022 | RUBEN VASQUEZ |
| Prkng lot landscape/Water mgmt | Cleared | 2/2/2022 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2022 | CELINA MORENO |
| Permit | Cleared | 2/18/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 2/18/2022 | CELINA MORENO |
| Sewer availability | Cleared | 2/18/2022 | CELINA MORENO |
| City Hist. Cultural Monument | Cleared | 3/8/2022 | KATIE DEBIASE |
| HPOZ | Cleared | 3/8/2022 | KATIE DEBIASE |
| Historic monument | Cleared | 3/8/2022 | KATIE DEBIASE |
| ZI | Cleared | 3/8/2022 | KATIE DEBIASE |
| Green Code | Cleared | 4/14/2022 | RICHARD GARCIA |
| DAS Clearance | Cleared | 4/21/2022 | SERGIO SILVA |
Contact Information
| Architect | Kaplan,, David Alan; Lic. No.: C12875 | 2419 PIER AVE. SANTA MONICA, CA 90405 |
| Contractor | Austin Commercial L P; Lic. No.: 806038-B | 3535 TRAVIS ST SUITE 300 DALLAS, TX 75204 |
| Engineer | Youssef,, Nabih Fouad Guirg; Lic. No.: S2026 | 550 S HOPE ST STE 1700 LOS ANGELES, CA 90071 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 12/8/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 12/9/2022 | Partial Inspection | ALAN MORELOS |
| Green Building Rough | 12/9/2022 | Not Ready for Inspection | ALAN MORELOS |
| METHANE-Barrier | 12/9/2022 | Approved | ALAN MORELOS |
| METHANE-Rough | 12/9/2022 | Approved | ALAN MORELOS |
| METHANE-Subgrade | 12/9/2022 | Approved | ALAN MORELOS |
| Wood Frame | 12/9/2022 | Partial Inspection | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | No Access for Inspection | ALAN MORELOS |
| Green Building Rough | 12/13/2022 | Not Ready for Inspection | ALAN MORELOS |
| Wood Frame | 12/13/2022 | No Access for Inspection | ALAN MORELOS |
| Excavation/Setback/Form/Re-Bar | 12/14/2022 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 12/14/2022 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Deputy Drilled-In Anchors | 12/16/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 12/16/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | ALAN MORELOS |
| Excavation/Setback/Form/Re-Bar | 12/22/2022 | Partial Approval | ALAN MORELOS |
| Footing/Foundation/Slab | 12/22/2022 | Partial Approval | ALAN MORELOS |
| Pre-Inspection | 12/22/2022 | Partial Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 1/25/2023 | Approved | MARTIN TAVITIAN |
| Deputy Drilled-In Anchors | 2/22/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Other (see comments) | 2/22/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 2/23/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Light Gage Steel Frame | 2/23/2023 | Approved | MARTIN TAVITIAN |
| Deputy Steel/Welding | 3/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 4/3/2023 | Partial Approval | MARTIN TAVITIAN |
| Light Gage Steel Frame | 4/3/2023 | Partial Approval | MARTIN TAVITIAN |
| Insulation | 4/27/2023 | Partial Approval | MARTIN TAVITIAN |
| Final | 8/9/2023 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Final | 8/9/2023 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Rough | 8/9/2023 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 8/9/2023 | SGSOV Not Required | ALAN MORELOS |
| Smoke Detectors | 8/9/2023 | Not Ready for Inspection | ALAN MORELOS |
| Structural Steel Frame | 8/9/2023 | Approved | ALAN MORELOS |
| Wood Frame | 8/9/2023 | Approved | ALAN MORELOS |
| Final | 11/7/2023 | Conditional Approval | MARTIN TAVITIAN |
| Green Building Final | 11/7/2023 | Approved | MARTIN TAVITIAN |
| Smoke Detectors | 11/7/2023 | Approved | MARTIN TAVITIAN |