4159 S KENYON AVE 90066
Certificate Information: 4159 S KENYON AVE 90066
- Application / Permit
- 21014-30000-03847
- Plan Check / Job No.
- B21WL03401
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodeling of a 1034 sf existing hom and a 706 sf addition consisting of 2 bedrooms and a bathroom. new roof to be added over kitchen and addition. *** see comments ***
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 12/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | KAVIAN REFAHI |
| Corrections Issued | 8/21/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 12/20/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 1/3/2022 | KAVIAN REFAHI |
| Plan Check Approved | 3/2/2022 | KAVIAN REFAHI |
| Issued | 3/2/2022 | APPLICANT |
| Building Plans Picked Up | 3/4/2022 | APPLICANT |
| CofO in Progress | 12/5/2022 | RICHARD STEINBACH |
| Permit Finaled | 12/5/2022 | DANIEL ORRANTE |
| CofO Issued | 12/5/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/5/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2021 | SAUL GARCIA |
| Low Impact Development | Cleared | 12/14/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | SAUL GARCIA |
Contact Information
| Architect | Justus,, John Karl; Lic. No.: C13537 | 1140 HUMBUG WAY AUBURN, CA 95603 |
| Contractor | Addition Building & Design Inc; Lic. No.: 925471-B | 4335 VAN NUYS BLVD STE 354 SHERMAN OAKS, CA 91403 |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/11/2022 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 3/14/2022 | Not Ready for Inspection | DAVID FEILER |
| Piling/Pier/Caisson | 3/14/2022 | Not Ready for Inspection | DAVID FEILER |
| Deputy Drilled-In Anchors | 3/18/2022 | Approved | CLAYTON GRAHAM |
| Excavation/Setback/Form/Re-Bar | 3/21/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/23/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 3/23/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2022 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/24/2022 | Approved | JESUS RODRIGUEZ |
| Wood Frame | 3/24/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/3/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/3/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 5/3/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 5/3/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/3/2022 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/9/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 5/9/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 5/13/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Wood Frame | 5/13/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 5/18/2022 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 5/18/2022 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/18/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 5/18/2022 | Approved | STEPHANIE SWANSON |
| Gas Test | 5/25/2022 | Approved | CLAYTON GRAHAM |
| Insulation | 5/25/2022 | Corrections Issued | CLAYTON GRAHAM |
| Shower Pan | 5/25/2022 | Approved | CLAYTON GRAHAM |
| Underground Mechanical | 5/25/2022 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 5/27/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 5/31/2022 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 5/31/2022 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 5/31/2022 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 5/31/2022 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/31/2022 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 6/1/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Drywall Nailing | 6/7/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 6/7/2022 | Partial Approval | STEPHANIE SWANSON |
| Drywall Nailing | 6/13/2022 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 6/15/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 6/16/2022 | Not Ready for Inspection | HERBERT GIRON |
| Drywall Nailing | 6/21/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 6/21/2022 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 10/24/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 10/28/2022 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 10/28/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/1/2022 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 11/1/2022 | Approved | JESUS RODRIGUEZ |
| Final | 11/15/2022 | Corrections Issued | HERBERT GIRON |
| Gas Test | 11/15/2022 | Approved | HERBERT GIRON |
| Green Building Final | 11/15/2022 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 11/15/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 11/15/2022 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Not Ready | HERBERT GIRON |
| Final | 11/28/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 11/28/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 11/28/2022 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/28/2022 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/28/2022 | SGSOV Approved | HERBERT GIRON |
| Pre-Inspection | 12/1/2022 | Conditional Approval | HERBERT GIRON |
| Final | 12/5/2022 | OK to Issue CofO | RICHARD STEINBACH |