5121 N TOPEKA DR 91356

Certificate Information: 5121 N TOPEKA DR 91356

Application / Permit
21014-30000-03846
Plan Check / Job No.
B21WL03400
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing covered patio with storage to ADU with new addition per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 4/7/2022
Issuing Office
Current Status
CofO Issued on 4/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2021 APPLICANT
Assigned to Plan Check Engineer 8/4/2021 MANUEL GARCIA
Corrections Issued 8/7/2021 MANUEL GARCIA
Applicant returned to address corrections 2/17/2022 JASON JANGADA
Applicant returned to address corrections 3/14/2022 ALFREDO JARA
Plan Check Approved 3/25/2022 ALFREDO JARA
Building Plans Picked Up 3/29/2022 APPLICANT
Issued 4/7/2022 APPLICANT
CofO in Progress 2/8/2023 DAVID SANDOVAL
Permit Finaled 4/7/2023 DANIEL ORRANTE
CofO Issued 4/7/2023 DANIEL ORRANTE
Permit Finaled 4/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/25/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 8/25/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/27/2021 GABRIEL ROBLES
Sewer availability Cleared 9/27/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 2/17/2022 MANUEL GARCIA

Contact Information

Contractor Omega Home Improvement Inc; Lic. No.: 842862-B 13720 VALLEYHEART DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/12/2022 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 4/15/2022 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 4/22/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Approval DAVID SANDOVAL
Insulation 5/16/2022 Partial Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 8/8/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 8/8/2022 Corrections Issued DAVID SANDOVAL
Green Building Rough 8/8/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 8/8/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 8/8/2022 Approved DAVID SANDOVAL
Gas Test 9/19/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 9/19/2022 Approved DAVID SANDOVAL
Rough-Elec/Plmb/HVAC 9/19/2022 Approved DAVID SANDOVAL
Sewer 9/19/2022 Corrections Issued DAVID SANDOVAL
Shower Pan 9/19/2022 Approved DAVID SANDOVAL
Sewer 9/27/2022 Approved SEAN WIRCH
Gas Test 9/29/2022 Not Ready for Inspection JESUS PINEDA
Sewer 10/5/2022 Approved SEAN WIRCH
BUILDING-Rough-Frame 10/7/2022 Approved DAVID SANDOVAL
Green Building Rough 10/7/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 10/7/2022 Approved DAVID SANDOVAL
Gas Test 10/13/2022 Partial Approval DAVID SANDOVAL
Sewer 10/13/2022 Approved DAVID SANDOVAL
Drywall Nailing 10/26/2022 Approved DAVID SANDOVAL
Final 1/23/2023 Corrections Issued DAVID SANDOVAL
Gas Test 1/23/2023 Approved DAVID SANDOVAL
Green Building Final 1/23/2023 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 1/23/2023 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 1/23/2023 Approved DAVID SANDOVAL
PLUMBING-Final 2/1/2023 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 2/1/2023 SGSOV Approved JUSTIN HAWLEY
ELECTRICAL-Final 2/7/2023 Approved DAVID SANDOVAL
Final 2/7/2023 OK to Issue CofO DAVID SANDOVAL
Green Building Final 2/7/2023 Approved DAVID SANDOVAL
HVAC-Final 2/7/2023 Approved DAVID SANDOVAL