2740 W GLASSELL ST 90026
Certificate Information: 2740 W GLASSELL ST 90026
- Application / Permit
- 21014-30000-03833
- Plan Check / Job No.
- B21WL03383
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Replace several windows and doors at the rear facade, and add new exterior storage space at front of house per engineering calcs
- Permit Issued
- Issued on 6/21/2022
- Issuing Office
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | JASON JANGADA |
| Corrections Issued | 8/3/2021 | JASON JANGADA |
| Applicant returned to address corrections | 9/18/2021 | JASON JANGADA |
| Applicant returned to address corrections | 1/20/2022 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 2/16/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 3/31/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 4/21/2022 | EDWIN ESPIN |
| Building Plans Picked Up | 4/25/2022 | APPLICANT |
| Applicant returned to address corrections | 5/5/2022 | RICHARD GARCIA |
| Plan Check Approved | 5/16/2022 | RICHARD GARCIA |
| Issued | 6/21/2022 | APPLICANT |
| CofO in Progress | 8/22/2023 | DONALD CRICHLOW |
| Permit Finaled | 8/23/2023 | DEROLD HAUFF |
| CofO Issued | 8/23/2023 | DEROLD HAUFF |
| Permit Finaled | 8/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/8/2021 | PATRICK MISCHLICH |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2021 | JEANIE LAM |
| GPI Written Notices | Cleared | 4/22/2022 | JASON JANGADA |
| Roof/Waste drainage to street | Cleared | 4/26/2022 | AMAAN MALIK |
Contact Information
| Contractor | J & S Construction Services Inc; Lic. No.: 988967-B | 5135 5TH AVENUE LOS ANGELES, CA 90043 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 7/15/2022 | Partial Approval | FREDDIE RIVERA |
| Insulation | 8/24/2022 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Deputy Drilled-In Anchors | 11/3/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/22/2022 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Barrier | 11/22/2022 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 11/22/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/5/2022 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 12/5/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/3/2023 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 2/3/2023 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 2/3/2023 | Approved | FREDDIE RIVERA |
| Deputy Wood Construction | 2/7/2023 | Conditional Approval | FREDDIE RIVERA |
| Deputy Wood Construction | 2/10/2023 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/24/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/24/2023 | Approved | FREDDIE RIVERA |
| Green Building Rough | 2/24/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/24/2023 | Approved | FREDDIE RIVERA |
| Final | 6/30/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 6/30/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/30/2023 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 6/30/2023 | Approved | FREDDIE RIVERA |
| Final | 8/22/2023 | OK to Issue CofO | DONALD CRICHLOW |