11907 W NORTH PARK AVE 90066
Certificate Information: 11907 W NORTH PARK AVE 90066
- Application / Permit
- 21014-30000-03832
- Plan Check / Job No.
- B21WL03382
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel (E) Single family dwelling. Per engineering design.
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- Issued on 3/2/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | ALFREDO JARA |
| Corrections Issued | 9/8/2021 | ALFREDO JARA |
| Quality Review Completed | 9/20/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 11/4/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 12/20/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 12/22/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 1/6/2022 | ALFREDO JARA |
| Plan Check Approved | 2/15/2022 | ALFREDO JARA |
| Issued | 3/2/2022 | APPLICANT |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/24/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 2/4/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 2/4/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/20/2022 | No Access for Inspection | PATRICK QUALEY |
| Footing/Foundation/Slab | 4/20/2022 | Partial Approval | PATRICK QUALEY |
| Wood Frame | 5/4/2022 | Partial Approval | PATRICK QUALEY |
| Deputy Drilled-In Anchors | 5/6/2022 | No Access for Inspection | PATRICK QUALEY |
| Footing/Foundation/Slab | 5/6/2022 | Approved | PATRICK QUALEY |
| PLUMBING-Rough | 5/6/2022 | Partial Approval | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | PATRICK QUALEY |
| ELECTRICAL-Rough | 7/15/2022 | Corrections Issued | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Partial Approval | PATRICK QUALEY |
| PLUMBING-Rough | 7/15/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Wood Frame | 7/15/2022 | Corrections Issued | PATRICK QUALEY |
| Deputy Wood Construction | 7/18/2022 | No Access for Inspection | PATRICK QUALEY |
| Deputy Wood Construction | 7/19/2022 | Conditional Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 7/28/2022 | Corrections Issued | STEPHANIE SWANSON |
| Wood Frame | 7/28/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 7/29/2022 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/1/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/2/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 8/2/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/18/2022 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/22/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 8/22/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/25/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/25/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/25/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 9/2/2022 | Approved | JESUS RODRIGUEZ |