2225 N NELLA VISTA AVE 90027

Certificate Information: 2225 N NELLA VISTA AVE 90027

Application / Permit
21014-30000-03809
Plan Check / Job No.
B21WL03361
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Garage conversion of (e) garage to ADU and addition of (n) garage per CA Govt Code 65852.2 (e)(1)(A)
Permit Issued
Issued on 7/12/2022
Issuing Office
Current Status
CofO Issued on 7/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 FELIPE HERNANDEZ
Corrections Issued 9/15/2021 FELIPE HERNANDEZ
Quality Review Completed 9/27/2021 TARIK SAOUD
Applicant returned to address corrections 1/13/2022 FELIPE HERNANDEZ
Applicant returned to address corrections 2/1/2022 FELIPE HERNANDEZ
Applicant returned to address corrections 2/18/2022 FELIPE HERNANDEZ
Applicant returned to address corrections 3/9/2022 FELIPE HERNANDEZ
Plan Check Approved 5/25/2022 FELIPE HERNANDEZ
Issued 7/12/2022 APPLICANT
Building Plans Picked Up 7/13/2022 APPLICANT
CofO in Progress 4/22/2024 JOSEPH MCGARRY
CofO in Progress 4/22/2024 SCOTT FINNILA
CofO in Progress 7/9/2024 SCOTT FINNILA
CofO Issued 7/9/2024 DEROLD HAUFF
Permit Finaled 7/9/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/4/2022 CHRISTOPHER ROCHA
Permit Cleared 2/4/2022 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 2/4/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 2/8/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 2/8/2022 CHRISTOPHER ROCHA
Grading Pre-Inspection Cleared 2/18/2022 FELIPE HERNANDEZ
Construction within easement Cleared 3/13/2022 TINA MIRANDA
Trees in Parkway Cleared 4/26/2022 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/4/2022 Partial Approval JOSEPH MCGARRY
Sewer 10/4/2022 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 10/19/2022 Conditional Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 1/26/2023 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Corrections Issued JOSEPH MCGARRY
Green Building Rough 1/26/2023 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 1/27/2023 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 4/11/2023 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 4/11/2023 Approved JOSEPH MCGARRY
Green Building Rough 4/11/2023 Approved JOSEPH MCGARRY
HVAC-Rough 4/11/2023 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 4/11/2023 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 6/1/2023 Approved JOSEPH MCGARRY
HVAC-Rough 6/1/2023 Approved JOSEPH MCGARRY
Insulation 6/1/2023 Conditional Approval JOSEPH MCGARRY
Interior/Exterior Lathing 6/1/2023 Partial Approval JOSEPH MCGARRY
Special/Order Compliance 6/1/2023 Corrections Issued JOSEPH MCGARRY
Drywall Nailing 8/25/2023 Approved LILIANA PORTILLO
Insulation 8/25/2023 Approved LILIANA PORTILLO
Shower Pan 8/25/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/21/2023 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 4/5/2024 Approved ROY SPAULDING
ELECTRICAL-Final 4/5/2024 Approved ROY SPAULDING
Final 4/5/2024 Not Ready for Inspection ROY SPAULDING
Footing/Foundation/Slab 4/5/2024 Approved ROY SPAULDING
Green Building Final 4/5/2024 Corrections Issued ROY SPAULDING
PLUMBING-Final 4/5/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Approved ROY SPAULDING
Smoke Detectors 4/5/2024 Approved ROY SPAULDING
Final 4/12/2024 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/12/2024 Approved ENRIQUE MIRELES
Final 4/18/2024 OK to Issue CofO JOSEPH MCGARRY
Special/Order Compliance 4/24/2024 Corrections Issued JOSEPH MCGARRY