2650 S BEVERLY DR 90034

Certificate Information: 2650 S BEVERLY DR 90034

Application / Permit
21014-30000-03787
Plan Check / Job No.
B21WL03342
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major Remodel and 2-Story Addition to an (E) 1-Story S.F.D w/Attached Garage
Permit Issued
Issued on 4/22/2022
Issuing Office
Current Status
CofO Issued on 2/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 DAVID CASTILLO
Corrections Issued 8/16/2021 DAVID CASTILLO
Quality Review Completed 8/26/2021 TARIK SAOUD
Applicant returned to address corrections 2/23/2022 DAVID CASTILLO
Plan Check Approved 3/24/2022 DAVID CASTILLO
Issued 4/22/2022 APPLICANT
Building Plans Picked Up 4/22/2022 APPLICANT
CofO in Progress 2/15/2024 OGANES TARAKHCHYAN
CofO in Progress 2/20/2024 OGANES TARAKHCHYAN
CofO in Progress 2/20/2024 OGANES TARAKHCHYAN
No Progress 2/21/2024 KENNETH NAGLE
CofO in Progress 2/21/2024 KENNETH NAGLE
Permit Finaled 2/29/2024 DANIEL ORRANTE
CofO Issued 2/29/2024 DANIEL ORRANTE
Permit Finaled 2/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/24/2021 DINAH GARIN
Sewer availability Cleared 11/24/2021 DINAH GARIN
Low Impact Development Cleared 2/1/2022 TA ANH
Frnt yard landscape/Water mgmt Cleared 2/3/2022 RICHARD REASER
Roof/Waste drainage to street Cleared 2/4/2022 DINAH GARIN
Grading Pre-Inspection Cleared 3/24/2022 DAVID CASTILLO

Contact Information

Architect 2347, Ocean Avenue; Lic. No.: C34990       VENICE, CA 90291
Contractor M & D Development & Construction Inc; Lic. No.: 736716-B 1617 S SHERBOURNE DRIVE      LOS ANGELES, CA 90035
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/17/2022 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 5/17/2022 Approved KEVIN SARGSYAN
METHANE-Subgrade 5/17/2022 Approved KEVIN SARGSYAN
Deputy Steel/Welding 6/9/2022 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 6/28/2022 Approved KEVIN SARGSYAN
Deputy Steel/Welding 7/19/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 12/7/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Partial Approval JOHNNY MIRANDA
HVAC-Rough 12/27/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 12/27/2022 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/27/2023 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Rough 1/27/2023 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 1/27/2023 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 2/2/2023 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Rough 2/2/2023 Approved ASHLEY THOMPSON
Green Building Rough 2/2/2023 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 2/2/2023 Partial Approval ASHLEY THOMPSON
METHANE-Rough 2/2/2023 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 2/6/2023 Not Ready for Inspection ASHLEY THOMPSON
Shower Pan 2/6/2023 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 2/8/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 2/14/2023 Approved ASHLEY THOMPSON
Insulation 2/14/2023 Approved ASHLEY THOMPSON
Drywall Nailing 4/17/2023 Approved ASHLEY THOMPSON
ELECTRICAL-Final 8/8/2023 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Final 8/14/2023 Approved MEL KHACHATOURIAN
HVAC-Final 9/7/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Final 9/11/2023 Approved CLAYTON GRAHAM
PLUMBING-Final 9/12/2023 Partial Approval ARAM AVEDISIAN
Final 9/28/2023 Not Ready for Inspection ARAM AVEDISIAN
Gas Test 9/28/2023 Approved ARAM AVEDISIAN
Green Building Final 9/28/2023 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 9/28/2023 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 9/28/2023 Approved ARAM AVEDISIAN
Final 2/2/2024 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 2/2/2024 Approved OGANES TARAKHCHYAN
Final 2/9/2024 Corrections Issued OGANES TARAKHCHYAN
Final 2/14/2024 OK to Issue CofO OGANES TARAKHCHYAN
Deputy Steel/Welding 2/20/2024 No Access for Inspection OGANES TARAKHCHYAN
Service/Power Release 2/20/2024 Approved OGANES TARAKHCHYAN