2650 S BEVERLY DR 90034
Certificate Information: 2650 S BEVERLY DR 90034
- Application / Permit
- 21014-30000-03787
- Plan Check / Job No.
- B21WL03342
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major Remodel and 2-Story Addition to an (E) 1-Story S.F.D w/Attached Garage
- Permit Issued
- Issued on 4/22/2022
- Issuing Office
- Current Status
- CofO Issued on 2/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | DAVID CASTILLO |
| Corrections Issued | 8/16/2021 | DAVID CASTILLO |
| Quality Review Completed | 8/26/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 2/23/2022 | DAVID CASTILLO |
| Plan Check Approved | 3/24/2022 | DAVID CASTILLO |
| Issued | 4/22/2022 | APPLICANT |
| Building Plans Picked Up | 4/22/2022 | APPLICANT |
| CofO in Progress | 2/15/2024 | OGANES TARAKHCHYAN |
| CofO in Progress | 2/20/2024 | OGANES TARAKHCHYAN |
| CofO in Progress | 2/20/2024 | OGANES TARAKHCHYAN |
| No Progress | 2/21/2024 | KENNETH NAGLE |
| CofO in Progress | 2/21/2024 | KENNETH NAGLE |
| Permit Finaled | 2/29/2024 | DANIEL ORRANTE |
| CofO Issued | 2/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2021 | DINAH GARIN |
| Sewer availability | Cleared | 11/24/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 2/1/2022 | TA ANH |
| Frnt yard landscape/Water mgmt | Cleared | 2/3/2022 | RICHARD REASER |
| Roof/Waste drainage to street | Cleared | 2/4/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 3/24/2022 | DAVID CASTILLO |
Contact Information
| Architect | 2347, Ocean Avenue; Lic. No.: C34990 | VENICE, CA 90291 |
| Contractor | M & D Development & Construction Inc; Lic. No.: 736716-B | 1617 S SHERBOURNE DRIVE LOS ANGELES, CA 90035 |
| Engineer | Warling,, Jeffrey Paul; Lic. No.: C43743 | 1792 PEREGRINE CT SIMI VALLEY, CA 93065 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/17/2022 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Barrier | 5/17/2022 | Approved | KEVIN SARGSYAN |
| METHANE-Subgrade | 5/17/2022 | Approved | KEVIN SARGSYAN |
| Deputy Steel/Welding | 6/9/2022 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/28/2022 | Approved | KEVIN SARGSYAN |
| Deputy Steel/Welding | 7/19/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 12/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Rough | 12/27/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/27/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/27/2023 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 1/27/2023 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 1/27/2023 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 2/2/2023 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/2/2023 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 2/2/2023 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 2/2/2023 | Partial Approval | ASHLEY THOMPSON |
| METHANE-Rough | 2/2/2023 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 2/6/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Shower Pan | 2/6/2023 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 2/8/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/14/2023 | Approved | ASHLEY THOMPSON |
| Insulation | 2/14/2023 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 4/17/2023 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 8/8/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Final | 8/14/2023 | Approved | MEL KHACHATOURIAN |
| HVAC-Final | 9/7/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 9/11/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 9/12/2023 | Partial Approval | ARAM AVEDISIAN |
| Final | 9/28/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Gas Test | 9/28/2023 | Approved | ARAM AVEDISIAN |
| Green Building Final | 9/28/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 9/28/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 9/28/2023 | Approved | ARAM AVEDISIAN |
| Final | 2/2/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 2/2/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 2/9/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 2/14/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 2/20/2024 | No Access for Inspection | OGANES TARAKHCHYAN |
| Service/Power Release | 2/20/2024 | Approved | OGANES TARAKHCHYAN |