11812 W NORTH PARK AVE 90066
Certificate Information: 11812 W NORTH PARK AVE 90066
- Application / Permit
- 21014-30000-03754
- Plan Check / Job No.
- B21WL03294
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-story ADU attached to (E) detached garage.PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 8/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | ALFREDO JARA |
| Corrections Issued | 8/18/2021 | ALFREDO JARA |
| Quality Review Completed | 8/30/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 12/8/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 3/15/2022 | ALFREDO JARA |
| Plan Check Approved | 3/20/2022 | ALFREDO JARA |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| Issued | 8/9/2022 | APPLICANT |
| CofO in Progress | 4/2/2024 | JESUS RODRIGUEZ |
| Permit Finaled | 4/2/2024 | DANIEL ORRANTE |
| CofO Issued | 4/2/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/2/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 10/5/2021 | SAUL GARCIA |
| Specific Plan | Cleared | 10/6/2021 | FREDDY GARCIA |
| Hydrant and Access approval | Cleared | 12/6/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 1/31/2022 | CHRIS PARK |
| Roof/Waste drainage to street | Cleared | 2/1/2022 | SAUL GARCIA |
Contact Information
| Contractor | Carmichael Maintenance & Construction; Lic. No.: 983154-B | P O BOX 451627 LOS ANGELES, CA 90045 |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/5/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/7/2022 | Partial Approval | JESUS RODRIGUEZ |
| Sewer | 10/7/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/17/2022 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 10/20/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 12/23/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 12/23/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 1/20/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Conditional Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/20/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/7/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 2/7/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Insulation | 2/8/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/2/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 3/2/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 3/2/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 3/2/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/17/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 3/17/2023 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 3/17/2023 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 4/28/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/5/2023 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 6/5/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/21/2023 | Approved | JESUS RODRIGUEZ |
| Final | 7/21/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 7/21/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/21/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 7/21/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 8/1/2023 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| Final | 4/1/2024 | OK to Issue CofO | JESUS RODRIGUEZ |