8744-8746 N RUFFNER AVE 91343

Certificate Information: 8744-8746 N RUFFNER AVE 91343

Application / Permit
21014-30000-03731
Plan Check / Job No.
B21WL03272
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Conversion of (E) Attached garage into JADU. PER GCS 65852.2(e)(1)(A) AND 65852.22. Remove new attached patio to the S.F.R
Permit Issued
Issued on 4/28/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 KAVIAN REFAHI
Corrections Issued 7/30/2021 KAVIAN REFAHI
Applicant returned to address corrections 12/14/2021 MARJAN SHENASI
Plan Check Approved 12/23/2021 JASON JANGADA
Building Plans Picked Up 6/3/2022 APPLICANT
No Progress 8/10/2022 JASON JANGADA
Plan Check Approved 4/28/2023 AMY GUEVARRA
Issued 4/28/2023 APPLICANT
CofO in Progress 7/29/2024 RAUL OLAGI
CofO Issued 8/13/2024 DANIEL ORRANTE
Permit Finaled 8/13/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/10/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 8/10/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/10/2021 DAGOVERTO GUERRERO
Watercourse Cleared 8/10/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/11/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 9/30/2021 KURT CORRAL
Construction within easement Cleared 11/30/2021 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/18/2023 Approved RAUL OLAGI
PLUMBING-Rough 1/29/2024 Corrections Issued CHRISTOPHER ROJAS
Sewer 1/29/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 2/1/2024 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 2/9/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 2/26/2024 Partial Approval CRAIG DAVIS
BUILDING-Rough-Frame 3/4/2024 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 3/28/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/28/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 4/16/2024 Approved RAUL OLAGI
PLUMBING-Rough 4/16/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 4/23/2024 Partial Approval RAUL OLAGI
HVAC-Rough 4/23/2024 Approved RAUL OLAGI
Insulation 4/23/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 4/23/2024 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 5/16/2024 Approved RAUL OLAGI
Drywall Nailing 5/28/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 5/28/2024 Approved RAUL OLAGI
Final 7/22/2024 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 7/22/2024 Approved RAUL OLAGI
Final 7/29/2024 OK to Issue CofO RAUL OLAGI