1700 S ARLINGTON AVE 90019
Certificate Information: 1700 S ARLINGTON AVE 90019
- Application / Permit
- 21014-30000-03692
- Plan Check / Job No.
- B21WL03255
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION TO (E) SFD AND CONVERT (E) GARAGE INTO LIVING ROOM EXTENSION TO (E) SFD COMPLY WITH DEPARTMENT ORDER effective date 02/12/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 11/5/2021
- Issuing Office
- Current Status
- CofO Issued on 3/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | ALFREDO JARA |
| Corrections Issued | 8/5/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 9/30/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 10/22/2021 | LUKE GONZALES |
| Plan Check Approved | 11/4/2021 | FERNANDO FLORES |
| Issued | 11/5/2021 | APPLICANT |
| Building Plans Picked Up | 11/5/2021 | APPLICANT |
| CofO in Progress | 3/22/2022 | WILLIAM MICHALAK |
| Permit Finaled | 3/23/2022 | BRUCE TODD |
| CofO Issued | 3/23/2022 | BRUCE TODD |
| Permit Finaled | 3/23/2022 | BRUCE TODD |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/23/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | CELINA MORENO |
| Community Plan Implem. Overlay | Cleared | 9/20/2021 | RAFAEL FONTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/19/2021 | Approved | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 11/24/2021 | Partial Approval | WILLIAM MICHALAK |
| METHANE-Barrier | 11/24/2021 | Not Ready for Inspection | WILLIAM MICHALAK |
| METHANE-Subgrade | 11/24/2021 | Partial Approval | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 12/7/2021 | Approved | WILLIAM MICHALAK |
| METHANE-Barrier | 12/7/2021 | Approved | WILLIAM MICHALAK |
| METHANE-Subgrade | 12/7/2021 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 12/22/2021 | Partial Approval | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 1/7/2022 | Partial Approval | WILLIAM MICHALAK |
| Green Building Rough | 1/7/2022 | Approved | WILLIAM MICHALAK |
| Insulation | 1/7/2022 | Approved | WILLIAM MICHALAK |
| METHANE-Rough | 1/7/2022 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 1/13/2022 | Approved | WILLIAM MICHALAK |
| Drywall Nailing | 1/20/2022 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 2/11/2022 | Approved | WILLIAM MICHALAK |
| Final | 2/11/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Final | 2/11/2022 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 2/11/2022 | SGSOV Approved | WILLIAM MICHALAK |
| Smoke Detectors | 2/11/2022 | Approved | WILLIAM MICHALAK |
| Final | 2/17/2022 | OK to Issue CofO | WILLIAM MICHALAK |