11685 1/2 W OXNARD ST 91606

Certificate Information: 11685 1/2 W OXNARD ST 91606

Application / Permit
21014-30000-03597
Plan Check / Job No.
B21WL03153
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert part of existing carport and add 2nd floor for ADU per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 12/10/2021
Issuing Office
Current Status
CofO Issued on 6/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 FELIPE HERNANDEZ
Corrections Issued 8/3/2021 FELIPE HERNANDEZ
Quality Review Completed 8/20/2021 TARIK SAOUD
Applicant returned to address corrections 11/10/2021 FELIPE HERNANDEZ
Plan Check Approved 11/10/2021 FELIPE HERNANDEZ
No Progress 11/10/2021 FELIPE HERNANDEZ
Plan Check Approved 11/30/2021 FELIPE HERNANDEZ
Issued 12/10/2021 APPLICANT
Building Plans Picked Up 12/10/2021 APPLICANT
CofO in Progress 6/1/2022 ARAM AVEDISIAN
Permit Finaled 6/7/2022 MICHAEL SMITH
CofO Issued 6/7/2022 MICHAEL SMITH
Permit Finaled 6/7/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/4/2021 CARLOS AGUILERA
"Q" conditions Cleared 9/3/2021 MAXFIELD VERMY
ZA Case Cleared 9/3/2021 MAXFIELD VERMY
ZA Case Cleared 9/3/2021 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 9/14/2021 CARLOS AGUILERA
Sewer availability Cleared 9/14/2021 CARLOS AGUILERA
Low Impact Development Cleared 9/30/2021 KHAING AYE
Roof/Waste drainage to street Cleared 10/4/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 10/22/2021 RUEL COLE

Contact Information

Contractor Daniel Pascuale; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

SGSOV-Seismic Gas S/O Valve 12/14/2021 SGSOV Not Ready MISAEL ESPARZA
Gas Test 12/17/2021 Corrections Issued MISAEL ESPARZA
Sewer 12/17/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 12/21/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 12/27/2021 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 12/29/2021 Partial Approval JOHN KIDWELL
Pre-Inspection 12/29/2021 Partial Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 1/24/2022 Partial Approval DEANDRE HOFFMAN
Deputy Wood Construction 2/4/2022 Conditional Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 2/25/2022 Corrections Issued MATT KELLERMAN
ELECTRICAL-Rough 2/25/2022 Corrections Issued MATT KELLERMAN
Green Building Rough 2/25/2022 Not Ready for Inspection MATT KELLERMAN
HVAC-Rough 2/25/2022 Approved MATT KELLERMAN
PLUMBING-Rough 2/25/2022 Approved MATT KELLERMAN
BUILDING-Rough-Frame 3/4/2022 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 3/4/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Partial Approval JACK KARGODORIAN
Green Building Rough 3/4/2022 Approved JACK KARGODORIAN
HVAC-Rough 3/4/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 3/4/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 3/14/2022 Conditional Approval CALEB MEISTER
Insulation 3/14/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 3/14/2022 Approved CALEB MEISTER
BUILDING-Rough-Frame 3/18/2022 Approved CALEB MEISTER
Drywall Nailing 3/18/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 3/31/2022 Partial Approval ARAM AVEDISIAN
Shower Pan 3/31/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 5/23/2022 Approved MATT KELLERMAN
Gas Test 5/23/2022 Corrections Issued MATT KELLERMAN
HVAC-Final 5/23/2022 Approved MATT KELLERMAN
PLUMBING-Final 5/23/2022 Corrections Issued MATT KELLERMAN
Service/Power Release 5/23/2022 Not Ready for Inspection MATT KELLERMAN
Final 5/26/2022 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 5/26/2022 Approved ARAM AVEDISIAN
Green Building Final 5/26/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 5/26/2022 Partial Approval ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 5/26/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 6/1/2022 Approved ARAM AVEDISIAN
Final 6/1/2022 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 6/1/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 6/1/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/1/2022 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 6/1/2022 Approved ARAM AVEDISIAN