10674 W ROCHESTER AVE 90024

Certificate Information: 10674 W ROCHESTER AVE 90024

Application / Permit
21014-30000-03473
Plan Check / Job No.
B21WL03028
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY HOUSE ADDITION w/ new attached garage and WITH ROOF TRUSS 1 OF 5
Permit Issued
Issued on 11/9/2021
Issuing Office
Current Status
CofO Issued on 8/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 FELIPE HERNANDEZ
Corrections Issued 7/26/2021 FELIPE HERNANDEZ
Quality Review Completed 8/11/2021 TARIK SAOUD
Applicant returned to address corrections 11/5/2021 FELIPE HERNANDEZ
Plan Check Approved 11/9/2021 FELIPE HERNANDEZ
Issued 11/9/2021 APPLICANT
Building Plans Picked Up 11/10/2021 APPLICANT
CofO in Progress 8/14/2023 STEPHANIE SWANSON
Permit Finaled 8/15/2023 DANIEL ORRANTE
CofO Issued 8/15/2023 DANIEL ORRANTE
Permit Finaled 8/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 8/2/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/10/2021 DINAH GARIN
Sewer availability Cleared 8/10/2021 DINAH GARIN
Trees in Parkway Cleared 9/2/2021 JOHN KIM
Low Impact Development Cleared 10/22/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 10/28/2021 ANTHONY MAINEZ
GPI Written Notices Cleared 11/9/2021 FELIPE HERNANDEZ
Grading Pre-Inspection Cleared 11/9/2021 FELIPE HERNANDEZ

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Arriola,, Kirby Norman; Lic. No.: C31416 PO BOX 5566      OXNARD, CA 93031
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/19/2022 Approved EVAN COOPER
METHANE-Subgrade 10/28/2022 Approved ANDREW NAVE
Underground Mechanical 11/1/2022 Partial Approval OGANES TARAKHCHYAN
METHANE-Barrier 11/14/2022 Conditional Approval ASHLEY THOMPSON
Deputy Drilled-In Anchors 11/22/2022 Approved ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 11/22/2022 Corrections Issued ASHLEY THOMPSON
METHANE-Barrier 11/22/2022 Approved ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 11/28/2022 Approved ASHLEY THOMPSON
Footing/Foundation/Slab 11/28/2022 Approved ASHLEY THOMPSON
METHANE-Barrier 11/28/2022 Approved ASHLEY THOMPSON
Deputy Wood Construction 12/9/2022 Conditional Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Corrections Issued ASHLEY THOMPSON
Deputy Wood Construction 1/3/2023 Conditional Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 1/4/2023 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/13/2023 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Rough 1/23/2023 Partial Approval CLAYTON GRAHAM
PLUMBING-Rough 1/25/2023 Approved JULIAN AMAYA
Deputy Drilled-In Anchors 1/30/2023 Conditional Approval JULIAN AMAYA
Excavation/Setback/Form/Re-Bar 1/31/2023 Partial Approval JULIAN AMAYA
HVAC-Rough 1/31/2023 Corrections Issued JULIAN AMAYA
BUILDING-Rough-Frame 2/3/2023 Conditional Approval JEREMY TODD
Green Building Rough 2/3/2023 Not Ready for Inspection JEREMY TODD
METHANE-Rough 2/3/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 2/7/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 2/7/2023 Approved STEPHANIE SWANSON
Green Building Rough 2/7/2023 Approved STEPHANIE SWANSON
HVAC-Rough 2/7/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 2/7/2023 Partial Approval STEPHANIE SWANSON
Shower Pan 2/7/2023 Not Ready for Inspection STEPHANIE SWANSON
Insulation 3/6/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 3/6/2023 Approved JESUS PINEDA
Shower Pan 3/6/2023 Approved JESUS PINEDA
Drywall Nailing 3/15/2023 Approved CLAYTON GRAHAM
ELECTRICAL-Final 5/11/2023 Approved JEREMY TODD
Gas Test 5/22/2023 Corrections Issued JESUS PINEDA
PLUMBING-Final 5/22/2023 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 5/22/2023 SGSOV Not Ready JESUS PINEDA
Smoke Detectors 5/22/2023 Approved JESUS PINEDA
Gas Test 5/26/2023 Approved BRENDAN LOONEY
HVAC-Final 5/26/2023 Approved BRENDAN LOONEY
PLUMBING-Final 5/26/2023 Corrections Issued BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Not Ready BRENDAN LOONEY
PLUMBING-Final 6/1/2023 Approved KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Approved KENNETH NAGLE
Service/Power Release 7/19/2023 Approved MICHAEL PELHAM
HVAC-Rough 7/24/2023 No Access for Inspection JEREMY TODD
Final 8/14/2023 OK to Issue CofO STEPHANIE SWANSON
Green Building Final 8/14/2023 Approved STEPHANIE SWANSON
Service/Power Release 8/14/2023 Approved STEPHANIE SWANSON