6459 W 83RD ST 90045
Certificate Information: 6459 W 83RD ST 90045
- Application / Permit
- 21014-30000-03455
- Plan Check / Job No.
- B21WL03005
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO AN ADU, ADD ADDITION TO ADU AND ADD AN ATTACHED STORAGE SHED AT REAR OF ADU. PER LAMC 12.22 A.33(c) AND (d). DESIGN PER LICENSED ENGR.
- Permit Issued
- Issued on 12/6/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2021 | ALFREDO JARA |
| Corrections Issued | 7/20/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 8/24/2023 | CAROLEAN BASMA |
| Applicant returned to address corrections | 10/26/2023 | CAROLEAN BASMA |
| Plan Check Approved | 11/20/2023 | CAROLEAN BASMA |
| Issued | 12/6/2023 | APPLICANT |
| CofO in Progress | 4/26/2025 | DAVID FEILER |
| Permit Finaled | 4/26/2025 | RICHARD STEINBACH |
| CofO Issued | 4/26/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/26/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | DINAH GARIN |
| Sewer availability | Cleared | 9/21/2021 | DINAH GARIN |
| Specific Plan | Cleared | 12/2/2021 | EDUARDO HERMOSO |
| Construction near power lines | Cleared | 1/3/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 9/8/2023 | JASON NG |
| Hydrant and Access approval | Cleared | 10/18/2023 | JOHN CONNEALLY |
Contact Information
| Contractor | Guideline Builders Inc; Lic. No.: 1021305-B | 2110 ARTESIA BLVD 886 REDONDO BEACH, CA 90278 |
| Engineer | Namvar,, Mohammad Alipour; Lic. No.: C39797 | 231 VISTA DEL MAR STE D REDONDO BEACH, CA 90277 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/5/2024 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 1/5/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 1/5/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 1/22/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 1/22/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 1/22/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 1/22/2024 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 1/22/2024 | Partial Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2024 | Conditional Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 1/24/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 1/31/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 1/31/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 1/31/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Sewer | 1/31/2024 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 1/31/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 2/7/2024 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 2/8/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 2/12/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 2/12/2024 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 2/12/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 6/6/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 6/6/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 6/6/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 6/6/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 6/6/2024 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 6/6/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 7/2/2024 | Approved | TEMISTOCLES CAAL |
| Final | 7/2/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 7/2/2024 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 7/2/2024 | Approved | TEMISTOCLES CAAL |
| Final | 4/26/2025 | OK to Issue CofO | DAVID FEILER |
| Green Building Final | 4/26/2025 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 4/26/2025 | SGSOV Approved | DAVID FEILER |