3030 S KELTON AVE 90034
Certificate Information: 3030 S KELTON AVE 90034
- Application / Permit
- 21014-30000-03318
- Plan Check / Job No.
- B21WL02882
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Two story addition and partial remodel of existing one-story S.F.D. *** 1 of 2 ***
- Permit Issued
- Issued on 12/30/2021
- Issuing Office
- Current Status
- CofO Issued on 5/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | RICHARD GARCIA |
| Corrections Issued | 7/20/2021 | RICHARD GARCIA |
| Quality Review Completed | 8/10/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 9/28/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 11/16/2021 | RICHARD GARCIA |
| Plan Check Approved | 11/23/2021 | RICHARD GARCIA |
| Building Plans Picked Up | 11/24/2021 | APPLICANT |
| Issued | 12/30/2021 | APPLICANT |
| CofO in Progress | 5/2/2023 | KENNETH NAGLE |
| Permit Finaled | 5/2/2023 | DANIEL ORRANTE |
| CofO Issued | 5/2/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/2/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 8/18/2021 | SAUL GARCIA |
| ZI | Cleared | 8/18/2021 | RUBEN VASQUEZ |
| Specific Plan | Cleared | 8/30/2021 | KEVIN ARUCAN |
| Grading Pre-Inspection | Cleared | 9/28/2021 | RICHARD GARCIA |
| Low Impact Development | Cleared | 10/5/2021 | ANDRES COVARRUBIAS |
| Address approval | Cleared | 10/7/2021 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | SAUL GARCIA |
| Green Code | Cleared | 11/16/2021 | RICHARD GARCIA |
Contact Information
| Architect | Rees,, Robert S; Lic. No.: C26934 | 3483 BARRY AVENUE LOS ANGELES, CA 90066 |
| Contractor | Rebuilt Homes Inc; Lic. No.: 1063540-B | 2201 N LAKEWOOD BLVD STE D643 LONG BEACH, CA 90815 |
| Engineer | Saleh,, Zouheir Toufic; Lic. No.: C42881 | 1304 CORTE MALTERA COSTA MESA, CA 92626 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/6/2022 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 1/12/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 1/14/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/4/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 3/7/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 5/9/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 5/9/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 5/9/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 5/9/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 5/16/2022 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 5/17/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/17/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 5/31/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/2/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/2/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/2/2022 | Approved | OGANES TARAKHCHYAN |
| Special/Order Compliance | 6/2/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/13/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 6/13/2022 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 6/13/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 6/13/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 6/13/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/16/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 6/16/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 6/16/2022 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 6/17/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 6/23/2022 | Approved | JOHNNY MIRANDA |
| Shower Pan | 7/7/2022 | Corrections Issued | HERBERT GIRON |
| Special/Order Compliance | 7/7/2022 | Partial Inspection | CLAYTON GRAHAM |
| Shower Pan | 7/11/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/13/2022 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 9/20/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Not Ready | HERBERT GIRON |
| ELECTRICAL-Final | 2/10/2023 | Corrections Issued | JOHNNY MIRANDA |
| Final | 2/10/2023 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 2/10/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 2/10/2023 | Approved | JOHNNY MIRANDA |
| MERV13>=Final | 2/10/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 2/10/2023 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 2/10/2023 | Approved | JOHNNY MIRANDA |
| Final | 2/16/2023 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 4/13/2023 | Approved | JOHNNY MIRANDA |
| Final | 4/13/2023 | OK to Issue CofO | JOHNNY MIRANDA |
| HVAC-Final | 4/13/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 4/13/2023 | Approved | JOHNNY MIRANDA |