3789 S ROSEWOOD AVE 90066
Certificate Information: 3789 S ROSEWOOD AVE 90066
- Application / Permit
- 21014-30000-03237
- Plan Check / Job No.
- B21WL02807
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story addition to the rear, (N) trellis patio cover in the front and kitchen remodel of an (E) SFD.
- Permit Issued
- Issued on 9/6/2022
- Issuing Office
- Current Status
- CofO Issued on 9/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | CHIHARU SUZUKI |
| Plans on Hold | 7/29/2021 | CHIHARU SUZUKI |
| Hold Released | 8/19/2021 | KAVIAN REFAHI |
| Corrections Issued | 8/30/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 3/8/2022 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 3/15/2022 | APPLICANT |
| Applicant returned to address corrections | 3/25/2022 | JASON JANGADA |
| Applicant returned to address corrections | 4/13/2022 | EDWIN ESPIN |
| Plan Check Approved | 4/14/2022 | EDWIN ESPIN |
| Issued | 9/6/2022 | APPLICANT |
| CofO in Progress | 9/5/2023 | RICHARD STEINBACH |
| Permit Finaled | 9/9/2023 | DANIEL ORRANTE |
| CofO Issued | 9/9/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/21/2022 | ALEXANDER HELFER |
Contact Information
| Contractor | Jsh Builders Inc; Lic. No.: 1062568-B | 1901 MARSHALLFIELD LN REDONDO BEACH, CA 90278 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/8/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 9/20/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/20/2022 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 11/16/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 11/16/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/16/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 12/21/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 12/21/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 12/21/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 12/21/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 12/21/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 1/6/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/6/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 1/9/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 3/14/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/22/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 8/22/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/22/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Final | 8/22/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 8/22/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 8/22/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 8/22/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/29/2023 | Approved | JESUS RODRIGUEZ |
| Final | 8/29/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Smoke Detectors | 8/29/2023 | Approved | JESUS RODRIGUEZ |