14561 W MULHOLLAND DR 90077

Certificate Information: 14561 W MULHOLLAND DR 90077

Application / Permit
21014-30000-03229
Plan Check / Job No.
B21WL02795
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2nd floor addition (430 sf) to (e) 2 story SFD (3,446 sf) w./ att. 2-car garage and complete remodel of SFD
Permit Issued
Issued on 12/9/2021
Issuing Office
Current Status
CofO Issued on 11/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 REZA HAGHIGHAT
Corrections Issued 8/3/2021 REZA HAGHIGHAT
Quality Review Completed 8/19/2021 TARIK SAOUD
Plan Check Approved 12/9/2021 REZA HAGHIGHAT
Issued 12/9/2021 APPLICANT
Building Plans Picked Up 12/9/2021 APPLICANT
CofO in Progress 11/7/2023 THOMAS FINNILA
Permit Finaled 11/30/2023 RUBEN SALAS
CofO Issued 11/30/2023 RUBEN SALAS
Permit Finaled 11/30/2023 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/2/2021 REZA HAGHIGHAT
Eng Process Fee Ord 176,300 Cleared 9/8/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 9/8/2021 GABRIEL ROBLES
Sewer availability Cleared 9/8/2021 GABRIEL ROBLES
Specific Plan Cleared 9/24/2021 OLGA AYALA
ZI Cleared 9/24/2021 OLGA AYALA
Hydrant and Access approval Cleared 11/19/2021 JOHN CONNEALLY

Contact Information

Architect Glass,, Scott J; Lic. No.: C31542 1134 ANGELO DR      BEVERLY HILLS, CA 90210
Contractor Cmf Homebuilders; Lic. No.: 827119-B 9903 SANTA MONICA BLVD #626      BEVERLY HILLS, CA 90212
Engineer Peck,, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/14/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Partial Approval JACK KARGODORIAN
Sewer 3/21/2022 Partial Approval MATT KELLERMAN
Deputy Drilled-In Anchors 3/22/2022 Conditional Approval MICHAEL TEMPLE
Deputy Drilled-In Anchors 4/28/2022 Conditional Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Approval JACK KARGODORIAN
Deputy Steel/Welding 5/27/2022 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 6/22/2022 Corrections Issued JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 8/12/2022 Partial Approval JACK KARGODORIAN
HVAC-Rough 8/12/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 8/12/2022 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 10/11/2022 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 10/11/2022 Corrections Issued THOMAS FINNILA
Green Building Rough 10/11/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 10/11/2022 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 10/31/2022 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 10/31/2022 Approved THOMAS FINNILA
Green Building Rough 10/31/2022 Approved THOMAS FINNILA
PLUMBING-Rough 10/31/2022 Approved THOMAS FINNILA
Deputy Wood Construction 11/3/2022 Conditional Approval MICHAEL SMITH
BUILDING-Rough-Frame 11/16/2022 Approved DANIEL ORRANTE
Insulation 11/16/2022 Approved DANIEL ORRANTE
Interior/Exterior Lathing 11/16/2022 Partial Approval DANIEL ORRANTE
Drywall Nailing 12/23/2022 Approved MATTHEW NELSON
Shower Pan 2/8/2023 Corrections Issued THOMAS FINNILA
Shower Pan 2/10/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 2/24/2023 Approved THOMAS FINNILA
Sewer 3/14/2023 Not Ready for Inspection THOMAS FINNILA
Gas Test 9/19/2023 Partial Approval MISAEL ESPARZA
Grounding or Bonding 9/28/2023 Not Ready for Inspection THOMAS FINNILA
Special/Order Compliance 10/7/2023 Corrections Issued MEL KHACHATOURIAN
HVAC-Final 10/11/2023 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Final 10/11/2023 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Final 10/17/2023 Partial Inspection THOMAS FINNILA
Service/Power Release 10/17/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 10/19/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 10/19/2023 Partial Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 10/24/2023 SGSOV Not Ready JUAN VALENZUELA
Final 10/26/2023 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 10/26/2023 Approved THOMAS FINNILA
Green Building Final 10/26/2023 Approved THOMAS FINNILA
Smoke Detectors 10/26/2023 Approved THOMAS FINNILA
Special/Order Compliance 10/26/2023 Approved THOMAS FINNILA
Service/Power Release 10/30/2023 Not Ready for Inspection THOMAS FINNILA
Final 11/2/2023 Partial Approval THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Approved THOMAS FINNILA
Service/Power Release 11/2/2023 Approved THOMAS FINNILA