7911 N PASO ROBLES AVE 91406

Certificate Information: 7911 N PASO ROBLES AVE 91406

Application / Permit
21014-30000-03200
Plan Check / Job No.
B21WL02776
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story addition (1,326) and remodel to (e) single story s.f.d. (1,218 sf) w./ att. 2-car garage (426 sf)
Permit Issued
Issued on 5/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 REZA HAGHIGHAT
Corrections Issued 7/26/2021 REZA HAGHIGHAT
Quality Review Completed 8/12/2021 TARIK SAOUD
Applicant returned to address corrections 3/21/2022 REZA HAGHIGHAT
Plan Check Approved 5/8/2022 REZA HAGHIGHAT
Building Plans Picked Up 5/10/2022 APPLICANT
Issued 5/16/2022 APPLICANT
CofO in Progress 5/28/2024 RAUL OLAGI
Permit Finaled 6/22/2024 RUBEN SALAS
CofO Issued 6/22/2024 RUBEN SALAS
Permit Finaled 6/22/2024 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 9/9/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 12/6/2021 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 12/29/2021 ROSE MARIE SMITH
Permit Cleared 1/26/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 1/26/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/7/2022 Not Ready for Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 7/7/2022 Corrections Issued DEANDRE HOFFMAN
Footing/Foundation/Slab 7/12/2022 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 8/5/2022 Corrections Issued RAUL OLAGI
Green Building Rough 8/5/2022 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 8/10/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 8/25/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 9/1/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 9/1/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 11/4/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/13/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 1/23/2023 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 2/21/2023 No Access for Inspection RAUL OLAGI
ELECTRICAL-Rough 2/21/2023 No Access for Inspection RAUL OLAGI
Green Building Rough 2/21/2023 No Access for Inspection RAUL OLAGI
HVAC-Rough 2/21/2023 No Access for Inspection RAUL OLAGI
PLUMBING-Rough 2/21/2023 No Access for Inspection RAUL OLAGI
ELECTRICAL-Rough 2/23/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 3/3/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/3/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 3/7/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 3/7/2023 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 4/7/2023 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 4/7/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 4/7/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 5/1/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/1/2023 Corrections Issued RAUL OLAGI
Green Building Rough 5/1/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 5/1/2023 Approved RAUL OLAGI
PLUMBING-Rough 5/1/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/9/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Approved RAUL OLAGI
Green Building Rough 5/9/2023 Approved RAUL OLAGI
PLUMBING-Rough 5/9/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/25/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 5/25/2023 Partial Approval RAUL OLAGI
Insulation 6/6/2023 Approved DAVID MATSON
Drywall Nailing 6/23/2023 Approved RAUL OLAGI
Shower Pan 7/11/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 7/31/2023 Approved RAUL OLAGI
Final 1/12/2024 Not Ready for Inspection RAUL OLAGI
Green Building Final 1/12/2024 Not Ready for Inspection RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Not Required RAUL OLAGI
Smoke Detectors 1/12/2024 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Final 5/28/2024 Approved RAUL OLAGI
Final 5/28/2024 OK to Issue CofO RAUL OLAGI
Green Building Final 5/28/2024 Approved RAUL OLAGI
HVAC-Final 5/28/2024 Approved RAUL OLAGI
PLUMBING-Final 5/28/2024 Approved RAUL OLAGI
Service/Power Release 5/28/2024 Approved RAUL OLAGI
Smoke Detectors 5/28/2024 Approved RAUL OLAGI