7911 N PASO ROBLES AVE 91406
Certificate Information: 7911 N PASO ROBLES AVE 91406
- Application / Permit
- 21014-30000-03200
- Plan Check / Job No.
- B21WL02776
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story addition (1,326) and remodel to (e) single story s.f.d. (1,218 sf) w./ att. 2-car garage (426 sf)
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | REZA HAGHIGHAT |
| Corrections Issued | 7/26/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 8/12/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 3/21/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 5/8/2022 | REZA HAGHIGHAT |
| Building Plans Picked Up | 5/10/2022 | APPLICANT |
| Issued | 5/16/2022 | APPLICANT |
| CofO in Progress | 5/28/2024 | RAUL OLAGI |
| Permit Finaled | 6/22/2024 | RUBEN SALAS |
| CofO Issued | 6/22/2024 | RUBEN SALAS |
| Permit Finaled | 6/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/9/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 12/6/2021 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2021 | ROSE MARIE SMITH |
| Permit | Cleared | 1/26/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 1/26/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/7/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 7/7/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 7/12/2022 | Approved | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 8/5/2022 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/10/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/25/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 9/1/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/4/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 1/23/2023 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/21/2023 | No Access for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 2/21/2023 | No Access for Inspection | RAUL OLAGI |
| Green Building Rough | 2/21/2023 | No Access for Inspection | RAUL OLAGI |
| HVAC-Rough | 2/21/2023 | No Access for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 2/21/2023 | No Access for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 2/23/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 3/3/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 3/3/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 3/7/2023 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 3/7/2023 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 4/7/2023 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 4/7/2023 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 4/7/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/1/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 5/1/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 5/1/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 5/1/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/1/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 5/9/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 5/9/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/9/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/25/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/25/2023 | Partial Approval | RAUL OLAGI |
| Insulation | 6/6/2023 | Approved | DAVID MATSON |
| Drywall Nailing | 6/23/2023 | Approved | RAUL OLAGI |
| Shower Pan | 7/11/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 7/31/2023 | Approved | RAUL OLAGI |
| Final | 1/12/2024 | Not Ready for Inspection | RAUL OLAGI |
| Green Building Final | 1/12/2024 | Not Ready for Inspection | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/12/2024 | SGSOV Not Required | RAUL OLAGI |
| Smoke Detectors | 1/12/2024 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Final | 5/28/2024 | Approved | RAUL OLAGI |
| Final | 5/28/2024 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 5/28/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 5/28/2024 | Approved | RAUL OLAGI |
| PLUMBING-Final | 5/28/2024 | Approved | RAUL OLAGI |
| Service/Power Release | 5/28/2024 | Approved | RAUL OLAGI |
| Smoke Detectors | 5/28/2024 | Approved | RAUL OLAGI |